ASBCA 61671
Board: ASBCA
Agency: Army
Appellant: Sea Cycle Construction Company
Date: 2018-10-25
Outcome: dismissed
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Sea Cycle Construction Company ) ASBCA No. 61671
)
Under Contract No. W91 B4L-1 O-C-0229 )
APPEARANCE FOR THE APPELLANT: Mr. Abdul J abar
Vice President
APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq.
Army Chief Trial Attorney
MAJ Bruce H. Robinson, JA
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE PROUTY
ON APPELLANT'S MOTION FOR RECONSIDERATION
After we dismissed this appeal for lack of jurisdiction because appellant,
Sea Cycle Construction Company (Sea Cycle), had not certified its claim, which was
for more than $100,000, Sea Cycle sent an email to the Board explaining that it did not
understand the concept of certifying a claim and that it wished to seek less than
$ i 00,000 if that would resolve the jurisdictional problem that it faced. By order dated
October 23, 2018, we deemed this email to constitute a request for reconsideration.
We are sympathetic to Sea Cycle, but must deny the motion for reconsideration.
As explained in our decision dismissing this appeal, if a contractor seeks more
than $100,000 in a claim to the government, it must certify that claim using language
that comports with the requirements of the Contract Disputes Act in 41 U.S.C. § 7103(b).
If it fails to do so, as it did here, we do not possess jurisdiction to consider the
appeal of the denial of the claim. See Kandahar Gravel Supplies and Logistics,
ASBCA No. 60531, 17-1 BCA ,i 36,688 at 178,632. Although we appreciate that
Sea Cycle may not have understood the finer points of the law involving our jurisdiction,
the contract at issue here incorporated by reference the standard Federal Acquisition
Regulation (FAR) 52.233-1, DISPUTES (MAY 2014) clause (see R4, tab 1 at 18,
incorporating the Disputes clause). That regulatory provision requires the certification
for claims greater than $100,000 and includes the language to be inserted into a claim
letter effecting the certification for such claims. See FAR 52.233-l(d)(2)(i), (iii). We
regret that Sea Cycle may have been confused, but the certification requirement is
jurisdictional and the contract did spell it out. We may not waive compliance with it.
Likewise, we have no basis to grant relief less than $100,000 if the original uncertified
claim was for greater than $100,000. Once a contractor has requested more than
$100,000 in relief in its claim, we may not remedy its jurisdictional flaw by granting
a lesser amount of damages. See WM Schlosser Co. v. United States, 705 F.2d 1336,
1338 (Fed. Cir. 1983) (Board without authority to waive certification requirement for
jurisdiction); cf Warchol Constr. Co. v. United States, 2 Cl. Ct. 384 (1983).
We grant motions for reconsideration only "if we have made a genuine
oversight that affects the outcome of the appeal." Relyant, LLC, ASBCA No. 59809,
2018 WL 4855178 at *2 (ASBCA Sept. 20, 2018). This is not such a case. The
request for reconsideration is denied.
Dated: October 25, 2018
J. REID PROUTY
Administrative Judge
Vice Chairman
Armed Services Board
of Contract Appeals
ROBERTT. PE
Administrative Judge
Armed Services Board
of Contract Appeals
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 61671, Appeal of Sea
Cycle Construction Company, rendered in conformance with the Board's Charter.
Dated:
JEFFREY D. GARDIN
Recorder, Armed Services
Board of Contract Appeals f
2