CBCA 4995
Board: CBCA
Appellant: Bass Transportation Services, LLC
Date: 2016-07-06
Outcome: dismissed
DISMISSED FOR LACK OF JURISDICTION: July 6, 2016
CBCA 4995
BASS TRANSPORTATION SERVICES, LLC,
Appellant,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
LeâMon J. Bass, III and LaMar Bass, co-owners of Bass Transportation Services,
LLC, Belleville, IL, appearing for Appellant.
Neil S. Deol, Office of Regional Counsel, Department of Veterans Affairs, Decatur,
GA, counsel for Respondent.
Before Board Judges HYATT, ZISCHKAU, and CHADWICK.
CHADWICK, Board Judge.
Bass Transportation Services, LLC (Bass or appellant), provided van transportation
to patients of a Department of Veterans Affairs (VA or respondent) medical facility in the
St. Louis, Missouri, area. VA terminated Bassâs contract for cause in August 2014. In
March 2015, Bass submitted a certified claim to the contracting officer for âdamagesâ
totaling $1,490,193.62 â[a]s a result of VAâs termination and breach.â The contracting
officer denied the claim in June 2015. Bass filed a timely appeal from that decision.
CBCA 4995 2
Although VA has now converted the termination to one for the convenience of the
Government, we must dismiss this appeal for lack of jurisdiction, because the underlying
claim necessarily questioned the validity of the termination for cause, which was no longer
reviewable by us when Bass filed the appeal. We cannot entertain an appeal of VAâs latest
contract action unless and until Bass submits a new claim and it is decided or deemed denied.
Background
The facts bearing on jurisdiction can be briefly stated. VA awarded van transportation
contract VA255-P-1771 to Bass in May 2011. Appeal File, Exhibit 2. VA exercised options
to continue the contract into 2014, Appeal File, Exhibit 3, but it terminated the contract for
cause after disputes arose about Bassâs performance obligations. Appeal File, Exhibits 7-11.
The VA contracting officer mailed Bass a notice terminating the contract in its entirety for
cause on August 29, 2014, but the letter was returned by the Postal Service, then resent and
received by Bass in early October 2014. Complaint, Exhibit F; Appeal File, Exhibit 14. The
notice said, among other things, that it âconstitute[d] a final decision that the contractor is
in default as specified and that the contractor has the right to appeal under the Disputes
clause.â Complaint, Exhibit F at 2. The contractâs Disputes clause, Appeal File, Exhibit 2
at 40, incorporated by reference Federal Acquisition Regulation (FAR) clause 52.233-1 (48
CFR 52.233-1 (2009)), which stated that a contracting officerâs decision was final unless the
contractor appealed or filed suit under the Contract Disputes Act (CDA), now codified at 41
U.S.C. §§ 7101-7109 (2012).1
On March 27, 2015, Bass submitted to the contracting officer, through outside
counsel, a five-page certified claim alleging that âVAâs Termination for Cause was a breach
of contract . . . and Bass is entitled to be awarded damages it incurred as a result of said
breach.â Appeal File, Exhibit 16 at 3 (respondentâs corrected copy, filed April 4, 2016).
Bass sought $1,090,616.50 in âlost profits for the remaining [unperformed] 104 weeks of the
Contractâ; $278,527.25 that Bass alleged it would have ârecouped to cover [startup] costs
during the remaining 104 weeks of the Contractâ; and $121,049.87 for âcontractual
obligations that Bass has and will continue to incur during the remaining 104 weeks of the
Contract,â including financing costs, mortgage interest, taxes, and insurance. Id. at 4. The
claim did not ask VA to convert the termination for cause to a termination for the
convenience of the Government, or ask for other relief from the termination decision itself.
1
The CDA was recodified without substantive change after the contract was
awarded, by Public Law No. 111-350, 124 Stat. 367 (2011).
CBCA 4995 3
A successor VA contracting officer issued a nine-page decision denying the claim on
June 30, 2015. Appeal File, Exhibit 16. After summarizing the contract, the history of the
dispute, and the claim, the contracting officer stated that â[t]he contract was properly
terminated for cause as a result of the Bass [sic] failure to perform,â and that â[g]iven the
propriety of the Governmentâs termination for cause, Bass is entitled to no measure of
damagesâ under the FAR. Id. at 6.