ASBCA 60710
Board: ASBCA
Date: 2016-07-25
ARMED SERVICES BOARD OF CONTRACT APPEALS
Petition of -- )
)
Volmar Construction, Inc. ) ASBCA No. 60710-910
)
Under Contract No. W912QR-12-C-0074 )
APPEARANCE FOR THE PETITIONER: Richard T. Garofalo, Esq.
Garrity, Graham, Murphy, Garofalo
& Flinn
East Hanover, NJ
APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq.
Engineer Chief Trial Attorney
Carlton A. Arnold, Esq.
Engineer Trial Attorney
U.S. Army Engineer District, Louisville
OPINION PURSUANT TO BOARD RULE l(a)(5)
DIRECTING CONTRACTING OFFICER TO ISSUE DECISION
Pursuant to Board Rule l(a)(5), Volmar Construction, Inc. (Volmar) petitions
the Board to direct the contracting officer (CO) to issue a decision on its claims in
advance of the date announced by the CO. In response, the government argues that the
CO's decision to issue the final decision no later than 31 March 2017 is reasonable
because the current CO has no prior knowledge of the claims and the government will
require an outside scheduling expert to examine the delay and impact damages.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE PETITION
1. On 29 September 2012, the United States Army Corps of Engineers,
Louisville District (government) awarded Contract No. W912QR-12-C-0074 to Volmar
to renovate and repair buildings on Joint Base McGuire-Dix-Lakehurst, New Jersey
(gov' t ex. 1, contract at 1-6).
2. By letter dated 19 May 2016, Volmar submitted eight claims to the CO,
seeking money and extensions of time. Volmar previously submitted the substance of
its claims to the CO as written demands for payment or requests for equitable
adjustment 1 as follows: $84, 191.11 for additional asbestos abatement, temporary
1
The Board expresses no opinion as to whether the previous submittals were claims or
requests for equitable adjustment.
heating costs, and inadequate water flow conditions dated 29 January 2016; $663,600.00
for extended office overhead dated 11 February 2016; $59,208.28 for kitchen
equipment 2 dated 12 February 2016; $930,584.74 for canopy modification and loss of
electrical subcontractor dated 22 February 2016; extension of time request for smoke
seals dated 29 February 2016; extension of time request for railings 3 dated 15 March
2016 4 ; $516,356.63 for additional labor, material testing, and extended office overhead
related to impacts and delays with peeling paint from the ceiling dated 21 March 2016 5 ;
and $41,868.06 and $34,808.08 for additional costs regarding installation of booster fans
dated 23 February 2016 and 31March2016 6 . (Gov't ex. 2, claim at 1-3)
3. By letter dated 27 June 2016, Volmar modified its two extension of time
claims by adding extended field office overhead in the amounts of $110,538.00 for the
railings claim and $202,756.50 for the smoke seals claim 7 (gov't ex. 6).
4. By letter dated 18 July 2016, the CO issued a final decision, granting the -
$59,208.28 claim for kitchen equipment (gov't ex. 7 at 1). The government attorney
sent a separate letter to Volmar, dated 18 July 2016, stating that the remaining seven
CO final decisions would be issued on or before 31 March 2017 (gov't ex. 8).
5. Pursuant to Board Rule l(a)(5), Volmar petitioned the Board, by letter dated
23 July 2016, for an order directing the CO to issue a decision on its seven remaining
claims no later than a reasonable time set by the Board (pet. at 4).
DECISION
When a CO receives a certified claim over $100,000, the Contract Disputes Act
(CDA), 41 U.S.C. §§ 7101-7109, requires that within sixty days of receipt of the
claim, the CO shall either (a) issue a decision or (b) notify the contractor of the time
2
Volmar submitted a notice of appeal regarding the kitchen equipment to the Board on
17 June 2016 and it was docketed as ASBCA No. 60634.
3
Volmar submitted a notice of appeal regarding the smoke seals and railings time
extensions on 17 June 2016 and it was docketed as ASBCA No. 60635.
4
In its 19 May 2016 claim, Volmar states that this prior submittal was dated
29 February 2016; however, the document in the record is dated 15 March 2016
(gov't ex.