CBCA 2294
Board: CBCA
Appellant: Americom Government Services, Inc.
Date: 2016-03-31
GRANTED IN PART: March 31, 2016
CBCA 2294
AMERICOM GOVERNMENT SERVICES, INC.,
Appellant,
v.
GENERAL SERVICES ADMINISTRATION,
Respondent.
Brendan M. Lill of Hogan Lovells US LLP, Washington, DC, counsel for Appellant.
Jennifer L. Howard, Office of General Counsel, General Services Administration,
Washington, DC, counsel for Respondent.
Before Board Judges POLLACK, GOODMAN, and SHERIDAN.
POLLACK, Board Judge.
This appeal involves the claim of Americom Government Services, Inc. (AGS or
appellant) against the General Services Administration (GSA) for costs of providing Host
Nation satellite licenses and bandwidth services (HNAs) for use by the United States Forces
Korea (USFK). For purposes of this decision we will use the identification HNAs to
collectively refer to both the license and frequency segments of the services. Where we need
to differentiate, we will specifically reference one or the other. Appellant seeks recovery
under indefinite delivery indefinite quantity (IDIQ) contract GS-35F-0301N (contract) and
task order number 9T3APN018 (task order), both of which were between GSA and AGS. On
June 22, 2005, appellant invoiced GSA for the HNAs in the amount of $569,793.53, plus an
additional $10,000 for training and translation services. GSA approved the payment and paid
appellant the full invoice. After payment of the invoice, GSA realized the HNAs were not
CBCA 2294 2
covered under the task order or any other contract instrument. GSA then sought to recoup the
money by deducting payments otherwise due appellant on other completed obligations. GSA
also returned $597,566.08 as unobligated funds to the Army. GSA closed out the task order
in May 2006.
While GSA does not deny that AGS provided HNAs and associated frequency services,
it denies AGSâs right to payment and questions the number of HNAs provided. GSA
contends that because the funds were not paid under a valid contract instrument and through
the authority of a contracting official, the payment was by mistake and appellant must bear
the consequences. GSA also raises defenses as to violating the cost ceiling on the contract.
Appellant initially claimed that the HNAs were covered under the task order, and that if not
covered, then there was an implied-in-fact contract. Finally, appellant ultimately asserted that
it was entitled to compensation under the theory of ratification.
On August 13, 2014, the Board ruled on cross-motions for summary relief in Americom
Government Services, Inc. v. General Services Administration, CBCA 2294, 14-1 BCA ¶
35,687. We ruled that as a matter of law, there was no express contract; determined that the
task order award was for no more than thirteen HNAs;, and determined that the task order did
not cover the added HNAs claimed. At the time of the motions, the only identified GSA
official to have a connection to the purchase of the HNAs was Ms. Elizabeth Bigger, who
approved the payment invoice for the work. We concluded that her actions as to the approval
of the invoice were not enough to create an implied-in-fact contract. We left unresolved the
matter of ratification, emphasizing that the record needed to be better developed before we
could render a decision.
On July 22 and 23, 2015, we held a hearing focusing on the issue of institutional
ratification. Significant evidence was presented at the hearing that had not been presented
previously, much of which is contained in this decision.
Witnesses
Most of the testimony was by telephone, with a number of key witnesses being
overseas. The following witnesses testified:
Roy Flores, an official with AGS at the time, testified as to his involvement with the
initial order for thirteen HNAs and as to AGS providing the HNAs, which are the subject of
the claim, to USFK. Appellant also called Don Rew, a principal of Integrated Satellite
Solutions (ISS), the Korean firm that provided the HNAs under subcontract to AGS. He
discussed interactions with USFK and AGS, the initiation of the purchase, what was
delivered, and when.
CBCA 2294 3
GSA called Elizabeth Bigger, the GSA official who approved the invoice/voucher for
the HNAs in dispute. She testified as to that approval, her role in procurement for GSA, and
the operation of the GSA procurement office. GSA also called Mr. Joseph Smithey, the
contracting officer (CO) from 2005 into 2008.