ASBCA 63630
Board: ASBCA
Agency: Army Corps of Engineers
Appellant: Colony Construction
Date: 2023-11-22
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Colony Construction ) ASBCA No. 63630
)
Under Contract No. W912WJ-22-P-0131 )
APPEARANCE FOR THE APPELLANT: Mr. Jay Harris
President
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Theresa A. Negron, Esq.
Engineer Trial Attorney
U.S. Army Engineer District, New England
OPINION BY ADMINISTRATIVE JUDGE SMITH
Proceeding pro se, appellant Colony Construction (Colony) challenges
respondent Army Corps of Engineersâ (USACEâs) default termination of Colonyâs
$156,000 contract. The parties elected to waive a hearing and submit the appeal on the
written record pursuant to Board Rule 11. USACE has shown sufficient grounds for
termination, and Colonyâs arguments do not rebut them. So, for the reasons stated
below, we deny the appeal.
FINDINGS OF FACT
On September 19, 2022, Colony was awarded a $156,000 contract to upgrade
the campground electrical system at West Thompson Lake, North Grosvenordale, CT,
with a completion date of February 24, 2023 (R4, tab 3; tab 5 at 68). 1 The premise of
the contract was to have the on-site work done prior to the 2023 recreation season
at the lake, which began on or about April 17, 2023 (R4, tab 2 at 12). The original
completion date was extended to require all physical construction to be completed by
April 17, 2023 (R4, tab 6 at 70).
The contract incorporated by reference clause 52.249-10 Default (Fixed-Price
Construction) (APR 1984), which allows the government to terminate the contract if
the contractor fails to prosecute the work in a timely manner or fails to complete the
1
The Rule 4 file contains 26 tabs in a single 164-page .pdf document. Our page
citations are to the .pdf page numbers 1-164, not the watermarked numbers
at the bottom of each page, or the internal pagination of each document.
work within the contractually agreed time. The clause further provides that the
contractorsâ right to proceed will not be terminated if the delays in completing the
work âarise[] from unforeseeable causes beyond the control . . . of the Contractor.â
(R4, tab 3 at 33).
Prior to beginning work in the field, the contract required preconstruction
submittals that included an initial progress schedule, quality control plan, accident
prevention plan, activity hazard analysis (AHA), construction site plan, work plan,
environmental protection plan and waste management plan (R4, tab 4 at 52-60). The
name and qualifications of a proposed testing organization and lead engineering
technician was subject to USACE approval (R4, tab 4 at 61). USACEâs response to
submittals could be, as appropriate, approval, disapproval, or a requirement for
revisions to the submittal identified in the governmentâs review remarks on the
submittal form (R4, tab 4 at 59-60).
Notice to proceed was issued on October 25, 2022 (R4, tab 5), but by
January 18, 2023, after several submittals that required revisions or were disapproved
(R4, tabs 7-8, 10-11), USACE summarized six insufficiencies in Colonyâs submittals
that were delaying the scheduled March 1, 2023, mobilization date (R4, tab 12).
Three of the six submittals required revisions and the other three had not been sent to
USACE at all (id.). 2 The summary review remarks of January 18 referred to the
earlier submittal responses which gave an explanation of each problem and how to
solve it (id.). In addition, a product data submittal was still absent (R4, tab 9 at 82).
After several more revisions, disapprovals, and comments, with Colonyâs
submittals still lacking necessary information (R4, tabs 12-17) and timely completion
unlikely, USACE issued a cure notice on February 16, 2023, requiring a remedy within
10 days (R4, tab 18). Colony acknowledged the cure notice on February 17, 2023 (R4,
tab 19), and revised two submittals that were again insufficient (R4, tabs 20, 23).
USACE issued a show cause notice on March 1, 2023, (R4, tab 24) to which
Colony again responded without actually fixing the submittals (R4, tabs 22, 25).
Colony indicated that it was âtoo lateâ for timely performance prior to the summer
season. Id.