CBCA 7344
Board: CBCA
Agency: Department of Veterans Affairs
Appellant: Construction Services Group, Inc.
Date: 2022-04-06
Outcome: denied
DENIED: April 6, 2022
CBCA 7344
CONSTRUCTION SERVICES GROUP, INC.,
Petitioner,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
Andy Moody, Vice President of Construction Services Group, Inc., Charleston, SC,
appearing for Petitioner.
Neil S. Deol, Office of General Counsel, Department of Veterans Affairs, Decatur,
GA, counsel for Respondent.
LESTER, Board Judge.1
Construction Services Group, Inc. (CSG) has filed a petition with the Board pursuant
to section 7103(f)(4) of the Contract Disputes Act (CDA), 41 U.S.C. § 7103(f)(4) (2018),
requesting that the Board direct a contracting officer with the Department of Veterans Affairs
(VA) to issue a decision on CSGâs certified claim, dated August 31, 2021, by a date certain.
The purpose of that statutory provision is to allow the contractor, if a decision of the
contracting officer is not forthcoming, to accelerate the date by which it can appeal a
âdeemed denialâ of its claim. Here, CSGâs claim is already âdeemed deniedâ because the
1
Pursuant to Board Rule 1(d) (48 CFR 6101.1(d) (2020)), â[t]he presiding judge
may without participation by other panel members decide . . . any petition.â Because
resolution of this petition does not raise novel issues, it is being decided by a single judge.
CBCA 7344 2
contracting officer neither issued a decision within sixty days after receiving CSGâs claim
nor timely extended the deadline for issuing that decision. For the same reasons that the
Board discussed in CTA I, LLC v. Department of Veterans Affairs, CBCA 5800, 17-1 BCA
¶ 36,829, we must deny the petition because the petitioner has already obtained the only
relief that we could effectively provide.
Background
On or about September 30, 2019, the VA awarded task order no. 36C24719N0948
under contract no. 36C24718D0140 to CSG for the renovation of Building 10 at the W.J.B.
Dorn VA Medical Center campus in Columbia, South Carolina. The original contract
completion date of January 13, 2021, was eventually extended through various contract
modifications to August 15, 2021.
On July 28, 2021, the VA contracting officer issued unilateral modification P00006,
increasing the contract price by $460,000 for a change involving porch repairs. Even though
the modification provided CSG with a price increase, the contracting officer requested that
CSG provide a cost proposal for the work referenced in the modification. In the
modification, the contracting officer indicated that, if CSG did not submit a cost proposal,
âconsideration will be given to issuing a settlement by determination based on the
governmentâs estimate of equitable cost and time.â
Instead of submitting a cost proposal, CSG on August 31, 2021, submitted a document
titled âRequest for Equitable Adjustment VA Renovations of Building 10â to the VA
contracting officer. In that document, CSG sought $415,339.74 in home office overhead
costs calculated under the Eichleay formula and an additional $204,385 as the â[d]elta
between MOD P00006 Proposal and Amount Added.â CSG indicated that it was entitled to
394 calendar days of compensable excusable delay (a number that it used to calculate the
amount of its home office overhead) and a total contract time extension of 180 calendar days.
As part of the submission, CSG signed a certification using the language set forth in Federal
Acquisition Regulation (FAR) 33.207 and requested âa decision to be issued within 60 days
of submission.â See 48 CFR 33.207 (2020) (FAR 33.207).
On September 14, 2021, CSG submitted what it titled âRevision 1 â Originally
Submitted 8/31/2021â to its âRequest for Equitable Adjustment VA Renovations of Building
10.â In this document, CSG addressed only its home office overhead request, slightly
reducing the amount and number of compensable excusable delay days requested from what
it had submitted on August 31, 2021.