CBCA 7512
Board: CBCA
Agency: Department of State
Appellant: Framaco International, Inc.
Date: 2024-04-18
Outcome: denied
THIS OPINION WAS INITIALLY ISSUED UNDER PROTECTIVE ORDER AND
IS BEING PUBLICLY RELEASED IN ITS ENTIRETY ON APRIL 29, 2024
DENIED: April 18, 2024
CBCA 7512
FRAMACO INTERNATIONAL, INC.,
Appellant,
v.
DEPARTMENT OF STATE,
Respondent.
Douglas L. Patin and Erik M. Coon of Bradley Arant Boult Cummings LLP,
Washington, DC; and Sam Z. Gdanski and Abraham S. Gdanski of Gdanski Law PC,
Teaneck, NJ, counsel for Appellant.
Thomas D. Dinackus, Matthew S. Tilghman, and Alexandra N. Wilson, Office of the
Legal Adviser, Buildings and Acquisitions, Department of State, Washington, DC, counsel
for Respondent.
Before Board Judges BEARDSLEY (Chair), RUSSELL, and O’ROURKE.
RUSSELL, Board Judge.
Appellant, Framaco International, Inc. (Framaco), has filed 129 appeals with the
Board (certain of which are consolidated) based on its contract with respondent, Department
of State (State or agency), Bureau of Overseas Building Operations (OBO), to construct an
embassy compound in Port Moresby, Papua New Guinea.
CBCA 7512 2
This decision is being issued under the Board’s order on further proceedings of
October 19, 2023 (Order), largely adopting the parties’ proposal to resolve approximately
100 of appellant’s non-consolidated appeals brought pursuant to Board Rule 53 (48 CFR
6101.53 (2023)) and certain claims in four of its consolidated appeals not based on
Government-caused delay. See Rule 53 (governing accelerated procedures available at an
appellant’s election, though limited to appeals involving disputes of $100,000 or less); see
also Rule 1(a) (“The Board may alter [its] procedures on its own initiative or on request of
a party to promote the just, informal, expeditious, and inexpensive resolution of a case.”).
The Order states that “[t]he presiding judge with the two members of the panel . . . will
decide the following appeals for which the parties will submit briefing: CBCA 7508, 7512,
7513, 7549, 7561, 7572, 7573, 7625, 7695, 7712, 7847, and 7859 (‘Selected Appeals’).” The
Order additionally states, “Decisions rendered by the panel will be in summary form either
in writing or orally, if a hearing is held; will be final and conclusive; will not be set aside,
except for fraud; and will not be precedential.”
As agreed to by the parties, quantum in the non-consolidated appeals and certain
claims in four of Framaco’s consolidated appeals (to which the Order applies) will be
decided based on a formula using Framaco’s prevailing damages in the Selected Appeals.
In a subsequent joint response docketed with the Board on March 19, 2024, the parties
confirmed their agreement that the Order applies to the appeals described above.
This appeal (CBCA 7512) arises from State’s final decision denying Framaco’s claim
for increased costs incurred for the installation of guard railings. We find that the contract
required Framaco to design and install these railings. The appeal is therefore denied.
Background
I. The Project
State awarded the embassy construction project to Framaco on July 6, 2015. The
project was originally designed in 2010 as a “Standard Secure mini-Compound” (SSmC)
with a scope that included a lock-and-leave new office building, a perimeter security wall
and fence, a main compound entry pavilion (MCAP), a service entry/utility building, and a
support annex. Appeal File, Exhibit 2 at DOS-PTMO-00982414.1 Construction of the
facility began in 2012, but in 2013, after forty percent of the project was completed, a future
marine detachment was planned for Port Moresby, and the embassy staffing requirement was
increased. Id. State then descoped the work under the 2012 contract and closed out that
1
All exhibits are found in the appeal file of CBCA 7512, unless otherwise noted.
CBCA 7512 3
contract. The project was redesigned under an expanded New Embassy Compound (NEC),
incorporating the completed portions of the SSmC project as well as surplus equipment and
materials, as appropriate. Id. The redesigned project included the perimeter security wall
and fence, the MCAP, a new service compound entry pavilion, a new four-story office
building, a marine service-guard residence, a service entry/utility building (SVC), an
enlarged support annex (SPX), and a new recreation facility. Id.
II.