ASBCA 63291
Board: ASBCA
Agency: Navy
Appellant: The Haskell Company
Date: 2024-02-22
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
The Haskell Company ) ASBCA No. 63291
)
Under Contract No. N40085-17-C-8331 )
APPEARANCE FOR THE APPELLANT: James E. Krause, Esq.
James E. Krause, PA
Jacksonville, FL
APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq.
Navy Chief Trial Attorney
Devin A. Wolak, Esq.
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE TAYLOR
ON THE GOVERNMENTâS MOTION FOR SUMMARY JUDGMENT
In this appeal, The Haskell Company (Haskell or appellant) seeks payment for
costs incurred due to unusually severe weather and seasonal differences allegedly
resulting from government project design changes on a joint reserve center that pushed
construction into adverse weather periods. The Navy filed a motion for summary
judgment asserting the Board should deny Haskellâs claim because the appellant
signed Modification No. A00001 (Mod 1) containing a release that resolved all costs,
impact effect, and delays and disruptions, arising out of or incidental to the project
design changes. Haskell opposes the motion alleging a material factual dispute exists
as to whether the parties intended the release to include appellantâs current claim.
Haskell also contends the Navyâs subsequent conduct manifested an intent in
contradiction of the release terms. Based upon the current record and drawing all
reasonable inferences in appellantâs favor, we deny the Navyâs motion since a material
factual dispute exists as to whether the parties had a meeting of the minds with regards
to the substance of the release.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
The parties filed numerous statements of facts and responses. 1 We set out the
relevant facts for the purpose of this motion below.
1
On January 13, 2023, the government filed âRespondentâs Statement of Undisputed
Material Facts in Support of its Motion for Summary Judgment.â On February 13,
2023, appellant filed âAppellantâs Response to Respondentâs Statement of
I. The Contract and Design Change Modification
1. On September 21, 2017, the Naval Facilities Engineering Systems
Command, Mid-Atlantic (NAVFAC or Navy) awarded firm fixed-price Contract
No. N40085-17-C-8331 (the contract) to Haskell to design and build a joint reserve
center in Des Moines, Iowa. (R4, tab 2.4 at 7614) 2
2. Haskell submitted a proposed design that included a sheet flow drainage
system (R4, tab 3.2 at 7752). NAVFAC accepted Haskellâs proposed design and
awarded it the contract (R4, tab 2.4 at 7616). The contract included FAR clauses
52.233-1, DISPUTES (MAY 2014), 52.242-14, SUSPENSION OF WORK (APR
1984), 52.243-4, CHANGES (JUN 2007), 52.249-10, DEFAULT (FIXED-PRICE
CONSTRUCTION) (APR 1984), and DFARS clause 252.243-7002, REQUESTS FOR
EQUITABLE ADJUSTMENT (DEC 2012) (id. at 7623-24). In its original baseline
schedule, Haskell indicated it intended to start construction on April 27, 2018 (R4,
tab 3.2 at 7896).
3. On April 4-5, 2018, Haskell provided its final completed design drawings to
the Navy for review (R4, tab 3.1 at 7723). During the design review process, the Navy
decided it wanted a different drainage system than the proposed slope-based site
drainage design (id. at 7723-24; app. supp. R4, tab 20 ¶ 7 (supplemental declaration of
Mr. Kenneth Duncan)). The parties agreed Haskell would make several design changes
and negotiated an estimated price for the changes with a 42-day time extension with
21-days being compensable (id. at ¶ 9).
Undisputed Material Facts in Support of Respondentâs Motion for Summary
Judgment.â Appellant, however, did not file a âStatement of Genuine Issues of
Material Factâ in accordance with Board Rule 7(c)(1).