ASBCA 58975
Board: ASBCA
Agency: NASA
Appellant: M. L. Energia, Inc.
Date: 2019-04-04
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
M. L. Energia, Inc. ) ASBCA No. 58975
)
Under Contract No. NAS 10-98025 )
APPEARANCE FOR THE APPELLANT: Bruce I. Afran, Esq.
Princeton, NJ
APPEARANCES FOR THE GOVERNMENT: Scott Barber, Esq.
NASA Chief Trial Attorney
Bradley W. Smith, Esq.
H. Joseph Batey, Esq.
Trial Attorneys
Kennedy Space Center, FL
OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD
ASBCA No. 58975 is the quantum phase of ML. Energia, Inc., ASBCA
No. 55947, 12-2 BCA i135,110 (MLE /), recon. granted in part, 13 BCA ~ 35,284
(MLE JI).* We have jurisdiction pursuant to the Contract Disputes Act of 1978 (CDA)
41 U.S.C. §§ 7101-7109. A two-day hearing on quantum was held in Trenton,
New Jersey, after which each party submitted an initial and reply brief. While
evidence was allowed at that hearing on entitlement/causation that exceeded the
quantum issues, the assigned judge did so in order to give appellant, by then with
counsel, a full opportunity to prove its case, with the understanding that objectionable
material would be handled as offered. (See discussion on the record at tr. 1/9-18) We
are thus not relying upon evidence in the record that goes to causation because those
issues were fully litigated and decided in the earlier proceedings. We now dismiss as
moot the government's Motion for Preliminary Ruling on Matters/Issues Excluded
from Further Litigation by Reason of Issue Preclusion.
In addition to the transcript of the 2016 hearing (with limits as outlined above)
and briefs filed thereafter, we also rely upon the record made in the entitlement
proceedings as well as the two decisions issued following those proceedings.
* Familiarity with our prior decisions in this matter is presumed.
FINDINGS OF FACT
NASA awarded a Small Business Innovation Research contract to Energia with
respect to photo-chemical remediation of sites contaminated with hazardous solvents
at the Kennedy Space Center, Florida. The contract was for a firm-fixed-price of
$597,960 but contemplated that Energia would contribute $100,000 to the project such
that the estimated cost of the project was around $697,960. MLE I at 172,395-96,
findings 3, 9, 14. Only the fixed-price amount is at issue here.
The research contract was not fully completed for reasons stated in our prior
decisions, and we found the government entitled to take an equitable reduction in
contract price under the FAR 52.246-7, INSPECTION OF RESEARCH AND DEVELOPMENT
-FIXED-PRICE (AUG 1996), clause of the contract. See MLE I at 172,396, finding 13;
MLE II at 173,170. The only issue remaining is whether the government is entitled to
all or some smaller portion of the amount withheld.
The contract clause (FAR 52.246-7) upon which the contracting officer (CO)
based her final decision (R4, tabs 1-2); and upon which we rely for making an
equitable reduction in the contract price, provides in relevant part as follows:
(e) The Government has the right to reject
nonconforming work. If the Contractor fails or is unable to
correct or to replace nonconforming work within the
delivery schedule (or such later time as the Contracting
Officer may authorize), the Contracting Officer may accept
the work and make an equitable price reduction. Failure to
agree on a price reduction shall be a dispute.
MLE I at 172,396, finding 13. Appellant makes much of the government failure to
provide a test site, basing it on evidence adduced in the quantum hearing. We found in
our first decision that:
The [test] sites at [Kennedy Space Center] eventually
became unavailable because appellant failed to adhere to
the timeline which would have made a test at the center
possible.
MLE I at 172,399, finding 36.
Thus, the lack of a site was the fault of Energia, not NASA. Pursuant to the
Inspection clause, where the contractor does not timely perform, the CO may accept
the work and make an equitable price reduction.