CBCA 5632
Board: CBCA
Agency: Department of Agriculture
Appellant: Foxy Construction, LLC
Date: 2017-03-13
Outcome: dismissed
DISMISSED FOR LACK OF JURISDICTION: March 13, 2017
CBCA 5632
FOXY CONSTRUCTION, LLC,
Appellant,
v.
DEPARTMENT OF AGRICULTURE,
Respondent.
Donna L. Gunther of Foxy Construction, LLC, Las Vegas, NV, appearing for
Appellant.
Heather R. Hinton-Taylor, Office of the General Counsel, Department of Agriculture,
Golden, CO, counsel for Respondent.
Before Board Judges HYATT, ZISCHKAU, and LESTER.
LESTER, Board Judge.
On February 7, 2017, the Board received and docketed an appeal filed by appellant,
Foxy Construction, LLC (FCL), from a contracting officerâs decision dated December 8,
2016. In reviewing the materials attached to the notice of appeal, the Board became
concerned about its jurisdiction to entertain this appeal and issued a show cause notice to
which both FCL and the United States Forest Service (USFS) (an entity within the
Department of Agriculture, the respondent in this appeal) have responded. Based upon our
CBCA 5632 2
review of those responses and the materials attached to them, we must dismiss this appeal
for lack of jurisdiction.
Background
On July 8, 2015, the USFS awarded contract no. AG-0261-C-15-0008 to FCL for the
relocation of a USFS bunkhouse and visitor center near Las Vegas, Nevada, with a total fixed
contract price of $358,591.50. The period of performance was originally set as ninety
calendar days after issuance of the notice to proceed, but with a completion date no later than
September 30, 2015 (a period less than ninety days from the contract award date).
Subsequently, the contract was modified to incorporate additional foundational and other
work, increasing the contract price to $392,438.90. The USFS also extended the contract
performance period several times, and the USFS has represented that the work required by
the contract was completed on April 22, 2016.
FCLâs First Monetary Request. On January 7, 2016, FCLâs owner sent an email
message to the USFS contracting officer and the contracting officerâs representative (COR),
asking them to âsee the attached documentation regarding the issues leading to a possible
back chargeâ and indicating that â[i]f you have any questions please give me a call.â
Attached to the email message was a letter on FCL letterhead, addressed to the âUnited
States Dept of Agriculture â Forest Service,â in which FCL stated that it was âasking to be
compensated for delays and for having to work in unusual conditionsâ and asserting that, by
the time the contract was awarded, it was already short of the ninety days that were
anticipated for contract performance. It represented that it had attempted to expedite
performance to complete the project before the winter months, but then appears to suggest
that design submittals were improperly rejected, which apparently delayed the project into
the winter months when weather issues made work on the project more difficult. It then
stated that it was attaching what it called a âclaimâ and asked that the contracting officer and
the COR âreview and commentâ on it, as follows:
Attached is a copy of the claim. Note the claim is because [the original
Government inspector] was injured and another inspector took over the project
who didnât trust [the first inspectorâs] decisions. Please review and comment.
In the letter, FCL then stated that, âwith a 70%-30% shared responsibility (70% Forest
Service & 30% Foxy), the backcharge should only be $51,051.47.â The attachments to the
letter included a âshut downâ cost calculation and a âloss of efficiency and productivityâ cost
calculation, which, added together, totaled $170,171.57. Thirty percent of $170,171.57 is
$51,051.47, which matches the amount of the backcharge request in the letter. Nevertheless,
also included in the attachments to the January 7 letter was an unsigned âApplication And
CBCA 5632 3
Certificate For Paymentâ apparently seeking payment (in the âCurrent Payment Dueâ
column) of $95,207.71.