ASBCA 61911
Board: ASBCA
Agency: Department of the Navy
Appellant: Strategic Technology Institute, Inc.
Date: 2022-01-05
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Strategic Technology Institute, Inc. ) ASBCA No. 61911
)
Under Contract No. N00178-05-D-4580 )
APPEARANCES FOR THE APPELLANT: James Y. Boland, Esq.
Caleb E. McCallum, Esq.
Venable, LLP
Tysons Corner, VA
APPEARANCES FOR THE GOVERNMENT: Arthur M. Taylor, Esq.
Chief Trial Attorney
Kara M. Klaas, Esq.
Trial Attorney
Defense Contract Management Agency
Chantilly, VA
OPINION BY ADMINISTRATIVE JUDGE DâALESSANDRIS
In April 2008, the Department of the Navy (Navy) awarded a contract to
appellant, Strategic Technology Institute, Inc. (STi), for engineering support and other
services. The contract was STiâs first cost-type contract, and the contract was
administered by the Defense Contract Management Agency (DCMA or government).
Pursuant to the contract, STi was required to submit an Incurred Cost Proposal (ICP)
within six months of the end of its fiscal year, which was the calendar year. STi
retained accountants to timely prepare its ICPs for the 2008 and 2009 fiscal years, in
2009 and 2010, respectively.
This appeals turns on the following factual dispute. STi contends that it timely
submitted the ICPs to the contracting officer. However, STi has not presented
documentary evidence or testimony from a witness with personal knowledge to
demonstrate that it submitted the documents. Conversely, the government maintains
logs of incoming mail (both email and hard-copy mail) and finds no record of
submission to the Navy or DCMA.
Following submission of an ICP, the normal procedure is for the Defense
Contract Audit Agency (DCAA) to audit the ICP, and for the contracting officer to set
final incurred cost rates. At the time of these events, DCAA monitored ICP
submissions based on the date of the last submission, and would send reminders to
contactors if the government had not received a new ICP within a year of the most
recent submission. However, because this was STiâs first cost-type contract, there was
no prior submission to trigger this reminder.
The situation remained unchanged until July 2014, with STi apparently of the
belief that its 2008 and 2009 ICPs were awaiting audit, and the government apparently
unaware that it had not received the 2008 and 2009 ICPs. During that month, DCAA
was auditing STiâs 2010 ICP, which would have been submitted in June 2011 -- three
years earlier. The auditor found reference to 2008 and 2009 costs, and requested from
STi copies of its 2009 and earlier ICPs. STi promptly provided the 2008 and 2009
submissions to DCAA. At this point in July 2014, the 2008 ICP had been prepared
five years earlier. In August 2014, DCAA internally considered the statute of
limitations and concluded that, since it had no record of the ICP having been submitted
previously, there was no statute of limitations problem, meaning that they concluded
that they had six years from the prior monthâs submission to bring any claim, rather
than a period of less than 11 months, that would apply if DCAA had received the
document back in July 2009. DCAA issued its audit report regarding the 2008 and
2009 ICPs in June 2015, just shy of six years from the original due date of the 2008
ICP, and just over a year prior to the expiration of the six year claim deadline for the
2009 ICP. The DCMA contracting officer eventually issued a final decision asserting
a government claim in excess of $1.1 million in November 2018, over three years after
the audit report was released and over nine years after the 2008 ICP was prepared, but
less than four-and-a-half years after DCAA requested the ICPs from STI in July 2014.
On appeal to the Board, STi argues that the governmentâs claim is barred by the
six-year statute of limitations. STi contends that it timely submitted the ICPs in
July 2009 and July 2010, more than six years before DCMA issued its final decision.
Alternatively, STi contends that, even if the Board finds that the ICPs were not
submitted until 2014, the governmentâs claim accrued in July 2009 and July 2010,
because the government should have known that STiâs ICPs were due on those dates.
STi has not presented any evidence on the merits of the governmentâs claim and states
that it is unable to defend against the governmentâs cost claims due to the passage of
time.