ASBCA 61871
Board: ASBCA
Agency: U.S. Army Corps of Engineers
Appellant: Meltech Corporation, Inc.
Date: 2026-02-06
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Meltech Corporation, Inc. ) ASBCA No. 61871
)
Under Contract No. W912DR-14-D-0021 )
APPEARANCES FOR THE APPELLANT: Leonard A. Sacks, Esq.
Leonard A. Sacks & Associates, P.C.
Rockville, MD
Fred A. Mendicino, Esq.
Faughnan Mendicino PLLC
Dulles, VA
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Adam J. Kwiatkowski, Esq.
Engineer Trial Attorney
U.S. Army Engineer District, Baltimore
OPINION BY ADMINISTRATIVE JUDGE CATES-HARMAN
This appeal arises from a contract between Meltech Corporation, Inc.
(âMeltechâ or âappellantâ), and the U.S. Army Corps of Engineers (âUSACEâ or
âgovernmentâ), specifically a Multiple Award Task Order contract that included both
Design-Build and Design-Bid-Build construction projects within the Baltimore District
Area of Responsibility, and the September 30, 2014, award by USACE of a Firm-
Fixed-Price Task Order No. 0002 to Meltech for all costs in connection with the
renovation, design, and construction of Building 8609, located at Ft. Meade, MD.
This appeal is related to fifteen total appeals that were consolidated. 1 This appeal
involves Meltechâs challenge to the government credit taken on the 24-gauge panels
for the metal roof.
1
ASBCA Nos. 61694, 61706, 61762, 61763, 61764, 61765, 61766, 61767, 61768,
61869, 61870, 61871, 61872, 62091, 62987. The lead appeal is ASBCA
No. 61694. Thirteen appeals were heard by the Board, and two appeals were
resolved on summary judgment. On December 17, 2021, a decision on
summary judgment was issued in ASBCA Nos. 61706 and 61768. On July 16,
2025, a decision was issued in ASBCA Nos. 61766, 61767 and 61872. On
January 6, 2026, a decision was issued in ASBCA No. 61765. On January 16,
2026, a decision was issued in ASBCA Nos. 61762 and 61764. Familiarity
with those decisions is presumed.
The Board has jurisdiction over these appeals under the Contract Disputes Act
of 1978, 41 U.S.C. §§ 7101-7109. A nine-day hearing was held via videoconference.
For the reasons stated below, we deny the appeal.
FINDINGS OF FACT
Contract and Task Order
1. On June 10, 2014, USACE issued a Request for Proposals (RFP) for a
Multiple Award Task Order Contract (MATOC) that included design-build and
design-bid-build construction projects within the Baltimore District area of
Responsibility. This was Phase 1 of a two-phase construction procurement. (Joint
Stipulations of Fact, General Background (JSOF GB) ¶ 1; R4, tab 2)
2. The MATOC included renovating several similar dormitory buildings
at Fort Meade, including Building 8609 (JSOF GB ¶ 3).
3. On August 14, 2014, USACE issued Amendment 0003 to RFP W912DR-
14-R-0003 for two seed projects under the MATOC to provide Design Criteria for the
Design-Build renovation of Building 8609 at Fort Meade and Building 4501
at Aberdeen Proving Ground. Each task order was to be awarded separately. (JSOF
GB ¶ 7)
4. On September 15, 2014, Meltech submitted its technical and cost proposals
for Building 8609âs renovation. Meltechâs proposal included a preliminary schedule.
According to this schedule, the design period would begin on November 18, 2014, and
end on June 4, 2015. The construction period would begin on May 29, 2015, and end
on April 26, 2016. (JSOF GB ¶¶ 11, 12)
5. On September 29, 2014, USACE awarded Meltech Base Contract
No. W912DR-14-D-0021. On September 30, 2014, USACE awarded Task Order
Contract No. 0002 to Meltech for the renovation of Building 8609 at Fort Meade. The
Task Order Contract provided Meltech with a 540-calendar day performance period
beginning from the Notice to Proceed date. The Notice to Proceed was issued on
November 17, 2014, and the original completion date was May 10, 2016. (JSOF GB
¶¶ 13-16)
Design Criteria
6.