CBCA 6708
Board: CBCA
Agency: Department of Veterans Affairs
Appellant: Archer Western Construction, LLC
Date: 2020-10-14
Outcome: granted
GRANTED IN PART: October 14, 2020
CBCA 6708
ARCHER WESTERN CONSTRUCTION, LLC,
Appellant,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
Larry W. Caudle, Jr., Brad C. Friend, and Jonathan J. Straw of Kraftson Caudle,
McLean, VA, counsel for Appellant.
Cecily Chamblis and Mark J. Villapando, Office of General Counsel, Department of
Veterans Affairs, Washington, DC, counsel for Respondent.
Before Board Judges GOODMAN, ZISCHKAU, and RUSSELL.
RUSSELL, Board Judge.
On October 2, 2020, the parties jointly moved for entry of a stipulated judgment in
the amount of $1,200,000.00 (settlement amount), to be paid to appellant, Archer Western
Construction, LLC (AWC), through the permanent indefinite judgment fund in accordance
with 31 U.S.C. § 1304 (2018). See 48 CFR 6101.25(b) (2018). The settlement amount is
inclusive of all costs, attorneysâ fees, and interest claimed by AWC on behalf of itself and
its subcontractors. The parties state that they will not seek reconsideration of, or relief from
the Boardâs decision, and they will not appeal the decision.
CBCA 6708 2
Decision
The Board GRANTS IN PART the appeal. AWC shall be paid $1,200,000.00
inclusive of costs, attorneysâ fees, and interest.
Beverly M. Russell
BEVERLY M. RUSSELL
Board Judge
We concur:
Allan H. Goodman Jonathan D. Zischkau
ALLAN H. GOODMAN JONATHAN D. ZISCHKAU
Board Judge Board Judge