ASBCA 59156
Board: ASBCA
Date: 2015-04-22
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Al Rafideen Company ) ASBCA No. 59156
)
Under Contract No. W91GDW-10-D-2000 )
APPEARANCE FOR THE APPELLANT: Mr. Ahmed Maithem Jassim
Owner
APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq.
Army Chief Trial Attorney
CPT Lyn P. Juarez, JA
Trial Attorney
OPINION BY JUDGE NEWSOM ON THE GOVERNMENT'S MOTION TO
DISMISS FOR LACK OF JURISDICTION
Appellant appeals from a contracting officer's final decision denying its
demand for payment. The government moves to dismiss this appeal for lack of
jurisdiction on the basis that appellant's demand was not a claim, because it was
neither signed nor certified as required by the Contract Disputes Act of 1978 (CDA),
41 U.S.C. §§ 7101-7109. Appellant did not submit an opposition to the government's
motion. For the reasons explained below, the Board grants the government's motion
and dismisses the appeal without prejudice for lack of jurisdiction.
STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
On 23 March 2010, the Joint Contracting Command-Iraq/Afghanistan awarded
Contract No. W91GDW-10-D-2000 to Al Rafideen Company for the procurement of
sand and related materials (R4, tab 1). The contract included Federal Acquisition
Regulation (FAR) clause 52.212-4, CONTRACT TERMS AND CONDITIONS -
COMMERCIAL ITEMS (MAR 2009) (R4, tab 1at48), subparagraph d of which stated
that the contract was subject to the CDA and incorporated FAR 52.233-1, DISPUTES.
On 28 July 2011, the contracting officer (CO) issued delivery order (DO) 0013
under the contract for 12,617 cubic meters of sand for $214,489 (R4, tab 5). In
September 2011, the CO notified appellant that it had no further need for sand under
DO 0013, and subsequently issued two bilateral modifications reducing the delivery
order quantities and related funding such that the total funding remaining after the
second modification was $69,956.51 (R4, tabs 8, 11, 15). The government asserts that
it made final payment to appellant in that amount on 21 February 2012 (R4, tab 16;
gov't br. at 1).
On 23 September 2013, appellant contacted the CO seeking compensation for
expenditures allegedly incurred on the contract in 2011 (R4, tab 18). After several
exchanges, appellant submitted a document entitled "Claim, Explanation, Invoices"
dated 7 October 2013 (R4, tabs 33, 34). The document lacked a signature,
certification, or stated total amount (R4, tab 34 ). The CO was able to calculate the
amount demanded to be $146,000 and notified appellant that "[ s]ince the claim is for
over $100,000 it will have to be certified." She attached FAR provisions showing the
required certification language. (R4, tab 35)
In response, appellant initially told the CO to "decrease" the amount claimed to
$98,000, but she again asked for a certification and again provided appellant the
required certification language (R4, tabs 36, 37). Appellant resubmitted its "Claim,
Explanation, Invoices" document, now dated 10 October 2013. This version included
a demand for $117,604.64 and stated: "First of all: I certify that the claim is made in
good faith." No additional certifying language, nor a signature, were included. (R4,
tab 38)
On 20 December 2013, the CO issued a final decision denying appellant's
purported claim (R4, tab 58). The contractor found errors in that decision (R4,
tabs 59-60) and thus the CO issued a corrected final decision on 30 December 2013
(R4, tab 61). On 11February2014, appellant submitted this appeal to the Board.
By letter dated 20 August 2014, the Board sua sponte advised appellant that the
"purported claim" in the record "d[id] not appear to contain a signature executing the
certification," nor did it contain all elements required in a certification, referring
appellant to several Board precedents. The Board directed appellant to demonstrate
that it submitted a certified claim to the contracting officer and provide a copy of that
claim to the Board. Appellant responded on 27 August 2014 by stating that it had
already provided the certified claim to the contracting officer. By letter dated
2 September 2014, the Board again directed appellant to provide a copy of the claim
and certification. Appellant responded by email that same day asking for clarification
on the missing certification assertions.