CBCA 7824
Board: CBCA
Agency: Department of the Interior
Appellant: BlueIce Construction LLC
Date: 2024-08-15
Outcome: denied
DENIED: August 15, 2024
CBCA 7824
BLUEICE CONSTRUCTION LLC,
Appellant,
v.
DEPARTMENT OF THE INTERIOR,
Respondent.
Bryan B. Arnold of Gordee, Nowicki & Blakeney LLP, Irvine, CA, counsel for
Appellant.
Lindsay Cronin, Office of the Regional Solicitor, Department of the Interior,
Anchorage, AK, counsel for Respondent.
Before Board Judges BEARDSLEY (Chair), SHERIDAN, and KULLBERG.
SHERIDAN, Board Judge.
The issue presented by this appeal is whether the contracting officer properly
terminated the contract for cause. As BlueIce Construction LLC (BlueIce) did not complete
the contract during the period of performance and has presented no compelling reasons
excusing its nonperformance, BlueIceâs termination for cause was proper and is upheld.
The appeal was submitted for decision on the written record pursuant to Rule 19 (48
CFR 6101.19 (2023)).
CBCA 7824 2
Background
On September 23, 2022, the Bureau of Land Management (BLM), a component of
the Department of the Interior (DOI), awarded an $86,412 commercial services contract to
BlueIce to remove and replace the glycol in the heating system of building 1003 at Fort
Wainwright, Alaska. The contract incorporated Federal Acquisition Regulation (FAR)
52.212-4(m) (48 CFR 52.212-4(m) (2022)), which provides, âThe Government may
terminate this contract, or any part hereof, for cause in the event of any default by the
Contractor, or if the Contractor fails to comply with any contract terms and conditions . . . .â
The contract stipulated: âAny additional work/cost above the obligated amount must
be approved via modification by a warranted contracting officer prior to commencement or
the vendor does so at their own risk/expense.â The statement of work (SOW) required
BlueIce to: (1) drain glycol from the heating system; (2) flush the system with cleaner;
(3) install new 50/50 glycol solution; and (4) perform quarterly sampling for one year. The
SOW provided that, â[w]hen removing old glycol, it must be verified that all heating system
coils/components have been properly drained of old glycol.â The SOW also provided that
after the trisodium phosphate (TSP) cleaning solution circulated through the system for
twenty-four hours, âit must be verified that all system coils/components have been properly
drained of the TSP solution before any new glycol is introduced into the system.â
The notice to proceed established a ninety-day contract performance period,
September 23 to December 23, 2022. The contract was transmitted to BlueIce by email,
and both identified Mike Wise as the Governmentâs point of contact (POC). Mr. Wise was
BLMâs maintenance mechanical supervisor; he had no contracting authority to obligate
funds or modify the contract. The contract did not designate a contracting officerâs
representative.
In its opposition to DOIâs motion for summary judgment, filed before the parties
elected to submit this case for decision on the written record, BlueIce submitted a declaration
by Ron Tash, an employee of Reagent World, Inc., which is a sister company of BlueIce that
provides management services to BlueIce. Declaration of Ron Tash (Dec. 6, 2023) (Tash
Declaration) ¶ 1. Mr. Tash stated that he called Mr. Wise in October 2022 to ask some
questions regarding the work. Id. ¶ 5. Mr. Tash claimed that, during the call, Mr. Wise told
him that every heating system component, coil, and part on each floor had to first be drained
of glycol and tested on each floor. Id. ¶ 6. According to Mr. Tash, Mr. Wise said that
BlueIce would have to make sure, on a floor-by-floor basis, that the TSP had been removed
from each heating system component and coil. Id. In a February 3, 2023, email to the
contracting officer, BlueIce alleged, instead, that its âtechnicians were informed onsite by
the POCâ of the increased contract requirements. A February 9, 2023, email from BlueIce
to the contracting officer similarly stated that, âwhen our technicians were onsite discussing
CBCA 7824 3
the scope with the POC, the POC informed our technician that we had to flush each floor
with the solution, clean each component[] of the system.â
In support of its motion for summary judgment, DOI submitted a declaration by Mr.
Wise that contradicts the allegations of BlueIce and Mr. Tash. Declaration of Michael D.
Wise (Nov. 3, 2023) (Wise Declaration). Mr.