CBCA 8012
Board: CBCA
Agency: Department of Veterans Affairs
Appellant: Delta T Jr, LLC
Date: 2025-07-25
Outcome: denied
MOTION FOR SUMMARY JUDGMENT DENIED: July 25, 2025
CBCA 8012
DELTA T JR, LLC,
Appellant,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
John Marshall Cook, Paul Marshall Ticer, and Evan Williams of Fox Rothchild, LLP,
Washington, DC, counsel for Appellant.
Marcia A. McCree, Office of General Counsel, Department of Veterans Affairs,
Washington, DC, counsel for Respondent.
Before Board Judges VERGILIO, KULLBERG, and KANG.
VERGILIO, Board Judge.
In an initial appeal (CBCA 8012), Delta T Jr, LLC (contractor) disputes the
termination for default of its contract with the Department of Veterans Affairs (agency). In
a second appeal (CBCA 8373), the contractor seeks payment, denied by the contracting
officer, based upon alleged breaches, delays, abuses of discretion, and bad faith by the
agency. The cases are consolidated for purposes of developing a single record.
The agency moves for summary judgment in the initial appeal, seeking affirmance of
the termination for default, on the theory that the contractor failed to perform in accordance
with the terms of the contract and directives of the contracting officer to remedy work. The
contractor contends that it satisfactorily fulfilled its contractual obligations. It asserts that
CBCA 8012 2
the contracting officer required work beyond the scope of the contract, such that the
contractor was not obligated to perform as directed. In particular, the contractor maintains
that failures cited in the notice of default were due to government designs and specifications,
as well as unusually severe weather under which the government-designed drainage system
failed.
It is undisputed that the contractor did not perform as the contracting officer directed.
However, under the motion, the facts needed to resolve the dispute are not established. That
is, the undisputed facts do not demonstrate that the contractor was obligated to remedy the
situation or comply with the directives of the contracting officer. Requiring repair would be
outside the scope of the contract if the performance failures or defects were due to
government-furnished designs and the contractor performed satisfactorily in completing the
construction pursuant to those designs. Accordingly, the motion is denied.
Background
The contract’s Disputes clause (MAY 2014) (Federal Acquisition Regulation (FAR)
(48 CFR 52.233-1 (2024))) specifies that the contractor “shall proceed diligently with
performance of this contract, pending final resolution of any request for relief, claim, appeal,
or action arising under the contract, and comply with any decision of the Contracting
Officer.” Appeal File, Exhibit 1 at 578. Further, the contract’s Default (Fixed-Price
Construction) clause (APR 1984) (48 CFR 52.249-10) provides that if a contractor refuses
to prosecute the work or any separable part, with the diligence that will ensure its completion
within the time specified in the contract, the Government may terminate the contractor’s right
to proceed. Id. at 579. The contract’s Warranty of Construction clause (MAR 1994)
(48 CFR 52.246-21) states:
(i) Unless a defect is caused by the negligence of the Contractor or
subcontractor or supplier at any tier, the Contractor shall not be liable for the
repair of any defects of material or design furnished by the Government nor for
the repair of any damage that results from any defect in Government-furnished
material or design.
Id.
Under a firm, fixed-price contract, the contractor expanded a cemetery. Among its
tasks, the contractor was to design, furnish, and construct the retaining wall at issue in
accordance with specifications and other contract requirements and to install an asphalt road.
After construction, the road developed cracks and showed other signs of failure. The
retaining wall showed signs of failure. The contracting officer directed the contractor to
CBCA 8012 3
correct defects in the supporting retaining wall and roadway, referencing the contract’s
Disputes clause. The parties engaged in various communications. After the contractor did
not take corrective action, the contracting officer issued a termination for default, based upon
the contractor’s failure to prosecute performance.