CBCA 3876
Board: CBCA
Agency: Department of Energy
Appellant: CH2M WG IDAHO, LLC
Date: 2017-09-07
Outcome: granted
GRANTED IN PART: September 7, 2017
CBCA 3876
CH2MWG IDAHO, LLC,
Appellant,
v.
DEPARTMENT OF ENERGY,
Respondent.
Mark J. Meagher and Phillip R. Seckman of Dentons US LLP, Denver, CO, counsel
for Appellant.
Margaret B. Hinman and Terri L. Ackerman, Office of Chief Counsel, Department
of Energy, Idaho Falls, ID, counsel for Respondent.
Before Board Judges SOMERS, SHERIDAN, and ZISCHKAU.
SHERIDAN, Board Judge.
This is an appeal from a Department of Energy (DOE) contracting officer’s final
decision on a $41,250,152 claim submitted by appellant CH2MWG IDAHO, LLC (CWI)
on contract DE-AC07-051D14516. The contract, awarded by DOE, involved clean-up of
nuclear sites located in and around Idaho, and was referred to as the Idaho Cleanup Project
(ICP contract).
The ICP contract was a cost-plus-incentive-fee (CPIF) contract which also had
provisions that allowed the parties to negotiate extra work on a cost-plus-fixed-fee (CPFF)
basis. Early in the contract, consistent with the Cost Accounting Standards (CAS), CWI
reallocated some general and administrative (G&A) costs negotiated under the CPIF contract
into the CPFF portion of the contract. This, and CWI’s continued allocation of G&A costs
CBCA 3876 2
into the CPFF portions of the contract, allowed it to earn greater fees than DOE anticipated.
The parties delayed quantifying the impact of the reallocation of costs during the pendency
of the contract. At the end of the contract, when the parties were unable to agree on how the
reallocation impact should be quantified, DOE unilaterally modified the contract to reallocate
the costs earned under the CPFF part of the contract into the CPIF portion of the contract,
thereby effecting a reduction in the incentive fees CWI earned and accomplishing what DOE
considered to be an equitable result. CWI disagreed with what it characterizes as DOE’s
unilateral modification of the contract, arguing that the contract did not allow DOE to
unilaterally change the payments provisions of the contract. CWI seeks $27,359,380 for
DOE’s unilateral actions and resultant reduction in the incentive fees arising out of the G&A
cost allocations.
DOE’s action also automatically reduced the payments it owed for safety fees earned
to CWI, called safe units, because the amounts earned were dependent on the incentive fees
earned. CWI seeks $5,985,811 for safe units.
Also, during the contract, in order to reduce the Integrated Waste Treatment Unit
(IWTU) construction costs, CWI transferred certain costs originally billed to the IWTU
capital project line item into the IWTU and Idaho Nuclear Technology and Engineering
Center (INTEC) operating expense line items. DOE originally agreed that the cost transfers
were proper, but later changed its mind. By DOE’s later disagreeing to the cost transfers,
CWI was unable to recover those costs because its costs had reached a not-to-exceed cost cap
that the parties negotiated on the IWTU construction project. CWI seeks $7,904,961 for the
cost transfers that were disallowed by DOE.
The parties each filed extensive briefs setting forth copious amounts of facts. We
fully reviewed the facts each party considered important to its arguments, but found that
since we concluded that this matter turned on contract interpretation, and the contract was
clear, it was largely unnecessary to recreate an extensive recitation of facts used by the
parties in their briefs.
Findings of Fact
1. The request for proposals and CWI’s proposal
On July 21, 2004, DOE issued a request for proposals (RFP) for what ultimately was
designated contract DE-RP07-0314516. The proposal was for a CPIF contract that included
cost and schedule performance incentives for performing work described in the statement of
work (SOW). The stated purpose of the RFP was to safely accomplish as much of DOE
Office of Environmental Management’s (DOE-EM’s) mission as possible within available
CBCA 3876 3
funding, and the SOW set forth extensive work to be performed through the contract
completion date.