CBCA 6783
Board: CBCA
Agency: Department of Veterans Affairs
Appellant: CTA I, LLC dba CTA Builders
Date: 2020-05-14
Outcome: granted
GRANTED: May 14, 2020
CBCA 6783
CTA I, LLC dba CTA BUILDERS,
Petitioner,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
John M. Manfredonia of Manfredonia Law Offices, LLC, Cresskill, NJ ; and William
E. Dorris of Kilpatrick Townsend & Stockton LLP, Atlanta, GA, counsel for Petitioner.
Neil S. Deol, Office of General Counsel, Department of Veterans Affairs, Decatur,
GA, counsel for Respondent.
Before Board Judges GOODMAN, KULLBERG, and CHADWICK.
CHADWICK, Board Judge.
CTA I, LLC dba CTA Builders (CTA) submitted a certified claim for $4.4 million to
a Department of Veterans Affairs (VA) contracting officer in January 2020. In March 2020,
the contracting officer timely advised CTA under 41 U.S.C. § 7103(f)(4) (2012) that he
would decide the claim, not within sixty days of submission, but by November 9, 2020,
284 days after submission. In early April 2020, CTA petitioned the Board under 41 U.S.C.
§ 7103(f)(4) and Board Rule 2(a)(2) (48 CFR 6101.2(a)(2) (2019)) for an order setting the
deadline for a decision or a deemed denial of the claim âno later than May 30, 2020,â which
CTA has extended in a brief to June 15, 2020. We grant the petition as modified.
CBCA 6783 2
Background
The parties partially settled an earlier appeal involving the same construction contract
two years ago. The Board stayed that case (CBCA 5826) in June 2018, noting our
âexpectation that it w[ould] be unstayed and consolidated with a future appeal filed after
contract completion, to resolve remaining claimsâ not settled in CBCA 5826 âfor Eichleay
damages, attorney fees, and consultant fees. The parties should promptly advise the Board,
should it appear that no second appeal will be filed.â Previously, VA had unsuccessfully
moved to stay CBCA 5826 âuntil the project [wa]s complete,â noting that CTA had âmade
clear that a second Claim is forthcoming.â CTA I, LLC v. Department of Veterans Affairs,
CBCA 5826, 18-1 BCA ¶ 36,995 (single-judge order).
VA terminated the contract for convenience in January 2019, although the current
contracting officer states in a declaration that he is not entirely sure how much work was
completed versus uncompleted. At that point, the matter fell through the cracks at VA.
A new contracting officer was assigned in November 2019. In late January 2020, CTA filed
the second certified claim that the parties had foreseen in 2018, but VA was not ready for
it. A month after receiving the claim, the contracting officer began seeking funding to retain
a claim consultant. In March 2020, the contracting officer and the project engineering office
exchanged emails about the duration and expected cost of a claim review. It was at this time
that the contracting officer promised CTA a decision by November 9, 2020. The contracting
officer advised us at the end of April 2020 that a âfunding request for claim consultant
servicesâ was âwith the VISN 6 Network Director for signature. The funding ha[d] not yet
been obtained and [wa]s not available to issue a solicitation . . . .â
Discussion
We may shorten a deadline to decide a claim that a contracting officer has set within
sixty days of receiving the claim âin the event of undue delay on the part of the contracting
officer.â 41 U.S.C. § 7103(f)(4); see Monster Government Solutions, LLC v. Department
of Justice, CBCA 2834, 12-2 BCA ¶ 35,153; Volmar Construction, Inc., ASBCA 60710-910,
16-1 BCA ¶ 36,519.
VA notes that CTA âhad the benefit of 362 days from the time of Contract termination
to the time it submitted its Claimâ and argues that the agency âdid not unduly delay the
matterâ or âset an unreasonable deadline for a final decision,â having âtaken [steps] to secure
a claims consultant well within the original 60-day review period.â VAâs projected timeline
to a decision includes ninety days of claim review, thirty days of ânegotiationâ with CTA,
and thirty days of decision ârouting/review,â among other activities.
CBCA 6783 3
CTA does not wish to wait any longer to appeal. It argues that âVA knew well over
a year ago that CTA would be submitting a second claimâ but VA âdid nothing . . . . This
pre-claim knowledge and . . . lack of advance planning [militates] against granting the VA
more time . . .