ASBCA 56711
Board: ASBCA
Date: 2013-01-29
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of-- )
Macro-Z-Technology ) ASBCA No. 56711
)
Under Contract No. N44255-04-D-9122 )
APPEARANCES FOR THE APPELLANT: James F. Nagle, Esq.
Adam K. Lasky, Esq.
Oles Morrison Rinker & Baker LLP
Seattle, WA
APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq.
Navy Chief Trial Attorney
Anthony K. Hicks, Esq.
Robyn M. McNish, Esq.
Trial Attorneys
OPINION BY ADMINISTRATIVE JUDGE PARK-CONROY
ON THE GOVERNMENT'S MOTION AND APPELLANT'S CROSS-MOTION
FOR PARTIAL SUMMARY JUDGMENT
At issue are the parties' cross-motions for partial summary judgment relating to
the Order of Precedence clause of the contract. The Navy's motion for partial summary
judgment asserts that ten of the claim items sought by appellant Macro-Z-Technology
(MZT) in this appeal are subject to the clause. MZT's cross-motion asserts that the
clause is void.
By a letter dated 26 June 2012, MZT's counsel advised the Board that MZT is no
longer pursuing a number of its claim items. These claims, including five that are
addressed in the Navy's motion, were dismissed with prejudice. Accordingly, the Navy's
motion as to the five claim items we dismissed is moot. For the reasons stated, with
respect to the five claim items remaining at issue, the Navy's motion is denied. MZT's
cross-motion is also denied.
STATEMENT OF FACTS FOR PURPOSES OF THE MOTIONS
On 15 July 2004, the Engineering Field Activity, Northwest Division, of the Naval
Facilities Engineering Command (NAVFAC) issued a Request for Proposals (RFP),
Solicitation No. N44255-04-R-9115, for a competitive "LARGE 8(a) MULTIPLE
AWARD CONSTRUCTION CONTRACT (MACC)." The design-build seed project
was identified as "MCON [Military Construction] P-041 FIRE STATION ADDITION
AND RENOVATION" and involved buildings 2526 and 121 at the Naval Air Station,
Whidbey Island, Oak Harbor, Washington. (R4, tab 2 at 14)
MZT submitted its proposal for the MACC on 19 August 2004. With respect to
the Fire Station seed project, the technical proposal narrative stated:
After reviewing the proposed scope of work and inspecting
the jobsite, our recommendation is to demolish the existing
building and construct a new facility. The cost of doing this
would be no more than renovating and adding on to [sic] the
existing building.
(R4, tab 6 at 1065) Drawings for the new facility prepared by Mr. Gregory Benton of
Belay Architects were included as part of MZT's proposal (gov't mot. ^ 6 and tabs A, B,
C).
It is undisputed that the following five design features were included in MZT's
proposal for the Fire Station seed project:
(a) attic space above the second floor for mechanical and storage area with
access stairs (gov't mot., tab A at 75, 77, tab C at 27, 50-52);
(b) roof overhang at the equipment bays (gov't mot., tab A at 77, tab C at
48-49);
(c) windows for the dormitory rooms on the second floor (gov't mot., tab
A at 75, 76, tab Cat 41);
(d) first floor window overhang shading device eyebrows and an entry
canopy (gov't mot., tab A at 76, tab C at 44-45); and
(e) apparatus direct access to Ranger Street through a new gate (gov't
mot., tab A at 70, 73, tab C at 27-28).
(Gov't mot. at 2-4; app. resp. at 2-4)
With respect to (e) above, the drawings also show a relocated gate and relocated
offset fence (gov't mot., tab A at 73). The proposal narrative states:
Site Constraints
...The apparatus have direct access to Ranger Street through a
new gate and the parking has been relocated to the north
opposite the existing parking access off of Ranger Street. The
24 displaced stalls have been replaced with 28 new stalls.
This will require repositioning a portion of the standoff fence
and the relocation of the existing gate. Access to the building
will be through this relocated gate.
(Gov't mot., tab A at 70)
An Indefinite Delivery, Indefinite Quantity (IDIQ) MACC, No. N44255-04-D-
9122, was awarded to MZT by NAVFAC on 29 September 2004 (R4, tab 10 at 1192-94).
Task Order (TO) No.