ASBCA 58634
Board: ASBCA
Agency: Air Force
Appellant: Parsons Evergreene, LLC
Date: 2018-09-05
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Parsons Evergreene, LLC ) ASBCA No. 5 8634
)
Under Contract No. FA8903-04-D-8703 )
APPEARANCES FOR THE APPELLANT: Douglas S. Oles, Esq.
James F. Nagle, Esq.
Adam K. Lasky, Esq.
Howard W. Roth III, Esq.
Oles Morrison Rinker & Baker LLP
Seattle, WA
APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq.
Air Force Deputy Chief Trial Attorney
Michelle D. Coleman, Esq.
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE CLARKE
ON THE GOVERNMENT'S MOTION TO PARTIALLY DISMISS
FOR LACK OF JURISDICTION
The Air Force (AF) moves to dismiss Section V of Parsons Evergreene, LLC's
(PE' s) certified claim for lack of jurisdiction. As decided in our decision on the larger
claim issued today, we have jurisdiction to consider this motion pursuant to the Contract
Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. We deny the motion.
DISCUSSION
The AF identifies the issue presented in its motion as:
Whether the Armed Services Board of Contract Appeals
has jurisdiction to decide the modified total cost claim in
section V of Parsons Evergreene, LLC's certified claim
dated 29 June 2012 when section V of the claim lacked
sufficient information and detail that would have allowed
the CO to meaningfully consider the claim?
(Gov't mot. at 4) (Footnotes omitted) Claim Section V was previously Request for
Equitable Adjustment (REA) No. 8 (id. at 8).
Summary Chronology
PE's REA No. 8 was submitted on 30 November 2011 (R4, tab 1540; gov't
mot. at 5). The AF did not agree with the REA and PE filed a certified claim on
29 June 2012 (R4, tab 21; gov't mot. at 8). A final decision denying the claim was
issued on 27 March 2013 (R4, tab 214; gov't mot. at 10). This appeal was docketed by
the Board on 24 April 2013. A hearing was held from 2 to 27 March 2015. The final
brief, PE's reply brief, was received by the Board on 25 May 2016. The AF's motion
to partially dismiss for lack of jurisdiction was received by the Board on 28 December
2017. Therefore, the AF's motion was filed after the case was fully litigated and over
five years from the AF's receipt of the claim.
PE's Claim
PE's 29 June 2012 detailed certified claim had 127 pages, 7 discrete sections,
only Section V (previously REA No. 8) is the subject of the AF's motion. Section V,
Government Management and Administration of the Design-Build Process during the
Build Phase, claimed $28,157,994; it was identified by PE as a Modified Total Cost
(MTC) claim. (R4, tab 21 at PDF 53, 56)
The Technical Review
Claim Section V was submitted to the AF Center for Engineering and the
Environment (AFCEE) (R4, tab 213 at 33 7) for technical evaluation. AFCEE issued the
results of its evaluation on 4 September 2012 (id. at 306). AFCEE reviewed the 22
"events" in Section V of the claim and recommended that AF "reject PE's unsupported
claim of a 'Cardinal Change' doctrine" 1 (id. at 307). The AFCEE discusses each
"event" in its 31-page report (id. at 306-3 7). The events were: Structural Change,
Structural Brick (id. at 309); Design Deficiencies-Denial of Design Flexibility (id.
at 311 ); Government Interference with Implementing Approved Design (id. at 312);
Issuance of Improper Cure Notice (id.); Title II Representative Malfeasance (id. at 313 );
Base Entry Issues (id. at 314); Final Inspection Process (id.); Late Material Submittals
Approvals (id. at 315); Standing Seam Metal Roof, Material Approvals (id. at 317);
EIFS versus Stucco (id.); Manhole 35 Asbestos Extension (id. at 319); TLF Windows
(id.); Delegation of Field Authority (id. at 321); Standing Seam Metal Roof, Oil Canning
(id.); TLF Windows (Size) (id. at 323); Retention Pond (id. at 324); TLF Mechanical
Room Noise and Vibration (id. at 327); Roof Steel and Walkway in VQ Roof (Catwalks)
(id.); High Temperature Hot Water (id.); Switch to Tri-Arch Paint (id. at 328); Sewage
in VQ Caused by CE Service Call (id.