ASBCA 62736
Board: ASBCA
Agency: United States Army Corps of Engineers
Appellant: Joint Venture WMV Brussels American School
Date: 2024-12-05
Outcome: dismissed
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Joint Venture WMV Brussels American ) ASBCA No. 62736
School )
)
Under Contract No. W912GB-17-C-0018 )
APPEARANCE FOR THE APPELLANT: Seamus Curley, Esq.
Stroock & Strook & Lavin, LLP
Washington, DC
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Pietro O. Mistretta, Esq.
Herbert J. Aldridge, Esq.
Engineer Trial Attorneys
U.S. Army Engineer District, Europe
OPINION BY ADMINISTRATIVE JUDGE OSTERHOUT
This appeal involves a dispute between the United States Army Corps of
Engineers (USACE or the government) and Joint Venture WMV Brussels American
School (JV WMV or appellant) concerning Contract No. W912GB-17-C-0018 (the
contract). Appellant initially filed the appeal with five counts in its Complaint, although
it and the government later jointly moved to dismiss Counts II through V. The Board
granted the joint motion. 1 Thus, the only portion of the Complaint remaining in this
appeal is Count I.
In Count I of the Complaint, appellant appeals the denial of a contract
interpretation claim submitted by JV WMV on July 8, 2020, arguing that USACE
embedded design specifications in the contract as opposed to performance specifications
as alleged by the government (see compl. 7; R4, tab 3). 2 The Complaint sought âa ruling
from the ASBCA interpreting the Contract to resolve this interpretation dispute, as the
nature of Contractâs specifications has broad implications with respect to the partiesâ
respective obligations and liabilities, including ultimate liability for the projectâs designâ
1
Appellant subsequently filed additional appeals with the Board, ASBCA Nos. 63689,
63690, and 63691, pertaining to the same contract. These appeals were settled,
and the Board dismissed them with prejudice on October 25, 2024.
2
Though the contract interpretation claim was signed, it was not purported to be
âcertifiedâ by JV WMV (see R4, tab 3 at 9).
(compl. at 15). In the joint request to dismiss Counts II through V, the parties further
addressed Count I, stating, âHowever, the underlying issue of Count I (i.e., whether the
contract contains design specifications or performance specifications) has manifested
itself in [requests for equitable adjustments (REAs)] that have been filed, including
primarily an REA submitted on 20 April 2021 (the âMechanical REAâ) regarding the
mechanical system at the building being erected under the partiesâ contract.â (Joint
Partial Motion to Dismiss at 1) JV WMV anticipated submitting the Mechanical REA at
the time it filed its complaint with the Board and that this REA would âseek a substantial
price adjustment and approximately one additional year in schedule reliefâ (see compl.
at 31). Indeed, the Mechanical REA sought more than 5.1 million euros 3 in damages and
910 days of schedule relief (app. resp. at 4). The parties provided further details about
the Mechanical REA in their motion, including that appellant had already submitted part
of an REA; was in the process of submitting supplemental REAs on the mechanical issue;
and that it âintends to convert the referenced REA and its supplements into one [or] more
[Contract Disputes Act (CDA)] claims, which Respondent will then respond to with a
Contracting Officerâs Final Decision, as required by the CDA.â (Joint Partial Motion to
Dismiss at 2)
The government filed a motion to dismiss the appeal due to a lack of jurisdiction.
In it, the government requested two possible forms of relief: 1) dismiss paragraphs 26
through 33 of the Complaint; or 2) dismiss ASBCA No. 62736 (govât mot. at 1). The
government opined that paragraphs 26 through 33 had not yet been presented to the
contracting officer for a final decision (id. at 2). Regarding dismissing the appeal in full,
the government stated that appellantâs request for contract interpretation has now been
converted to a monetary claim that has not been presented to the contracting officer, and
a final decision has not been requested (id.).