ASBCA 62982
Board: ASBCA
Agency: Air Force
Appellant: APTIM Federal Services, LLC
Date: 2022-04-28
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
APTIM Federal Services, LLC ) ASBCA No. 62982
)
Under Contract No. FA9101-16-D-0006 )
APPEARANCES FOR THE APPELLANT: Robert G. Barbour, Esq.
Timothy E. Heffernan, Esq.
Joseph Figueroa, Esq.
Watt, Tieder, Hoffar & Fitzgerald L.L.P.
McLean, VA
APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq.
Deputy Chief Trial Attorney
Capt Jheremy Perkins, USAF
Lt Col Matthew Ramage-White, USAF
Trial Attorneys
OPINION BY ADMINISTRATIVE JUDGE THRASHER
APTIM Federal Services, LLC (APTIM or appellant) appeals from a denial of its
claim for operational costs incurred for a construction contract during a roughly two-
month period of time that the commander of Arnold Air Force Base, TN, closed the base
in order to mitigate the spread of SARS-Cov-2 (COVID-19). Appellant elected to
proceed under Rule 12.3, Accelerated Procedure, and both parties agreed to waive a
hearing and submit their cases on the written record pursuant to Board Rule 11. Only
entitlement is before us. The Air Force (AF or government) invokes the sovereign act
affirmative defense, and argues that since appellant did not dispute this defense in its
initial brief after being made aware of it, it has waived any opposition. While we are not
convinced that appellant has waived its opposition, we find the base closure to be a
sovereign act and deny the appeal.
FINDINGS OF FACT
1. The government awarded Contract No. FA9101-16-D-0006 to CB&I Federal
Services LLC, a predecessor in interest to APTIM Federal Services, LLC, located in
Alexandria, VA (R4, tab 1 at 2, tab 5 at 1). This contract was for design-build
construction work at Arnold Engineering Development Complex at Arnold Air Force
Base (AFB), TN, and contained Federal Acquisition Regulation (FAR) 52.242-14,
SUSPENSION OF WORK (APR 1984), FAR 52.233-01, DISPUTES (MAY 2014) and
FAR 52.243-04, CHANGES (JUN 2007) (R4, tab 1 at 3, 14, 35).
2. On July 15, 2019, the AF issued Task Order 96 for design-build work âfor
mounting the future AEDC High Pressure Air Bottle Farmâ with a period of performance
of â180-Calendar Days from issuance of Notice to Proceedâ (R4, tab 7 at 1-2). This
period of performance was extended through two bilateral modifications to June 25, 2020
(R4, tabs 9-10).
3. Due to the COVID-19 global pandemic, the baseâs Commander issued a
memorandum on April 3, 2020, closing Arnold AFB to all non-operationally urgent
personnel until further notice, effective April 6, 2020 (R4, tab 11 at 2). Appellant was not
deemed operationally urgent, and thus was unable to access the base during this period
(R4, tab 16). This restriction lasted until the Commander issued a second memorandum
on June 3, 2020, which rescinded the previous memorandum as of June 15, 2020, while
establishing other mitigation measures that allowed APTIM to enter the base and resume
its work (R4, tab 22).
4. APTIM submitted a certified claim on June 23, 2020, for $99,076 for
administrative costs it incurred during the roughly two months during which it was not able
to access the job site, as well as a day-for-day extension, totaling 59 days (R4, tab 23). The
government responded the following day, requesting more documentation justifying the
cost, and stated âplease be aware that the Sovereign Acts Doctrine establishes that actions
taken by the United States in its sovereign capacity shield it from contractual liability for
those actsâ and that it âintends to invoke the Sovereign Acts defense with regard to any
expenses related to actions taken in response to the COVID-19 pandemicâ (R4, tab 24).
However, the AF expressed willingness to extend the period of performance, which it
ultimately did, to November 30, 2020 (id., R4, tab 28 at 3).
5. Appellant provided supplemental information to substantiate its claim on
May 5, 2021, reducing the amount requested to $96,033.87 (R4, tab 29). The
government then issued a contracting officerâs final decision, denying the monetary
portion of the claim on June 24, 2021, recognizing that this was a firm-fixed price
contract which âplaces upon the contractor maximum risk and full responsibility for all
costs and resulting profit or lossâ (R4, tab 31 at 2) (emphasis omitted).
6.