ASBCA 62957
Board: ASBCA
Agency: U.S. Army Corps of Engineers
Appellant: Derian, Inc.
Date: 2023-08-25
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Derian, Inc. ) ASBCA No. 62957
)
Under Contract No. W912EF-19-C-0006 )
APPEARANCE FOR THE APPELLANT: Mr. Mark Jensen
President
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Michaela M. Murdock, Esq.
Engineer Trial Attorney
U.S. Army Engineer District, Walla Walla
OPINION BY ADMINISTRATIVE JUDGE TAYLOR
ON THE GOVERNMENTâS MOTION FOR PARTIAL RECONSIDERATION
The government moves for a partial reconsideration of the Boardâs August 25,
2023, decision granting, in part, the appeal of Derian, Inc., ASBCA No. 62957,
23-1 BCA ¶ 38,425 (familiarity with that decision is presumed). The government
requested the Board reconsider two rulings. First, the government requests the Board
reconsider its inclusion of $13,156 for the foot valves in its calculation of the contract
price. Second, the government requests the Board reconsider its ruling denying the
governmentâs liquidated damages assessment. For the reasons stated below, we deny the
governmentâs motion.
DECISION
I. Standard Of Review For Motions For Reconsideration
In deciding a motion for reconsideration, the Board will determine ââwhether there
is newly discovered evidence or whether there were mistakes in the decisionâs findings of
fact, or errors of law.ââ CJW Contractors, Inc., ASBCA No. 63228, 23-1 BCA ¶ 38,402
at 186,602 (quoting ADT Constr. Grp., Inc., by Timothy S. Cory, ASBCA No. 55358,
14-1 BCA ¶ 35,508 at 174,041). A motion for reconsideration does not give the moving
party another opportunity to âpresent arguments previously made and rejected.â Assist
Consultants Inc., ASBCA Nos. 61525, 62090, 21-1 BCA ¶ 37,946 at 184,297. A motion
for reconsideration also does not give the moving party the opportunity to advance
arguments that âproperly should have been presented in an earlier proceeding.â Dixon
v. Shinseki, 741 F.3d 1367, 1378 (Fed. Cir. 2014) (citing Bluebonnet Sav. Bank, F.S.B.
v. United States, 466 F.3d 1349, 1361 (Fed. Cir. 2006). Accordingly, the moving party
bears the burden to present ââa compelling reason why the Board should modify its
decision.ââ CJW Contractors, Inc. 23-1 BCA ¶ 38,402 at 186,602 (quoting Philips
Lighting N. Am. Corp., ASBCA No. 61769 et al., 21-1 BCA ¶ 37,821 at 183,647).
II. The Governmentâs Assertions Of Error
A. The Boardâs Inclusion of the Foot Valves in the Contract Price
Calculation Is Correct
In its motion for reconsideration, the government first asserts that the Board erred
in awarding Derian costs for the foot valves (govât mot. at 2-4). The government
misinterprets our decision. Our decision found the amount the government determined
Derian was entitled to for the foot valves in its final decision should be included in the
contract price. Derian, 23-1 BCA ¶ 38,425 at 186,760 (citing to finding 48 at 186,749).
Contrary to the governmentâs assertion, our decision did not award Derian an additional
monetary amount for the foot valves. In its response to the governmentâs motion for
reconsideration, Derian correctly notes that failing to include the foot valves in the
contract price would result in an underpayment to Derian (app. resp. at 3).
Our decision established the final contract price resulting from the governmentâs
deductive change and Derianâs various equitable adjustment claims. Derian, 23-1 BCA
¶ 38,425 at 186,760. The contract price following the governmentâs issuance of
Modification No. A00004 on May 13, 2021, was $2,263,279.71. Id. at 186,749 (finding 46).
In our decision, we used $2,263,279.71 as the starting point for calculating the correct
contract price. This amount did not include the foot valves. The government added the foot
valves claim amount to the contract price via Modification No. A00005 on August 4, 2021
(govât mot. at ex. 1). 1 Hence, we correctly found that we must include the foot valve amount
in our contract price calculation. The governmentâs subsequent submittal of Modification
No. A00005 with its motion does not change that conclusion.
The parties do not dispute that the total amount paid to Derian under the contract
was $2,044,870.41. Derian, 23-1 BCA ¶ 38,425 at 186,760. This amount included
payment for the foot valves (app. resp. at 2).