CBCA 6621
Board: CBCA
Agency: Department of Agriculture
Appellant: ITS Group Corp
Date: 2021-01-07
Outcome: denied
DENIED: January 7, 2021
CBCA 6621, 6747
ITS GROUP CORP,
Appellant,
v.
DEPARTMENT OF AGRICULTURE,
Respondent.
Porcia Hopkins, President of ITS Group Corp, Southhaven, MS, appearing for
Appellant.
Jennifer McVey Thomas, Office of the General Counsel, Department of Agriculture,
Juneau, AK, counsel for Respondent.
Before Board Judges SOMERS (Chair), ZISCHKAU, and CHADWICK.
SOMERS, Board Judge.
The United States Department of Agriculture (USDA) awarded a contract to ITS
Group Corp to paint various buildings in a remote area of Alaska. Because ITS Group failed
to paint the buildings to the contracting officerâs satisfaction, the contracting officer refused
to pay ITS Group progress payments for the work performed. When ITS Group appeared
to have vacated the job site, the contracting officer issued a cure notice. In response, ITS
Group failed to provide adequate assurance that it could complete the work. The contracting
officer terminated the contractor for default.
CBCA 6621, 6747 2
ITS Group initially appealed the denial of the claim for progress payments. Later, ITS
Group appealed the termination for default. Based upon the record and for the reasons
explained below, we deny ITS Groupâs appeals.
Background
On August 8, 2018, USDA solicited bids for the painting of eight buildings in the
Kenai Lake Work Center (KLWC), a remote area located in Alaskaâs Chugach National
Forest. The solicitation encouraged potential bidders to travel to Chugach and to visually
inspect the buildings prior to placing a bid on the contract. The contract incorporated
standard clauses, including Federal Acquisition Regulation (FAR) 52.246-12 (Inspection of
Construction), FAR 52.236-3 (Site Investigation and Conditions Affecting the Work), FAR
52.236-2 (Differing Site Conditions), and FAR 52.232-5 (Payments Under Fixed-Price
Construction Contracts).
On July 18, 2019, USDA awarded the firm fixed-price contract to ITS Group, a small
business located in Southaven, Mississippi. The contracting officer issued the notice to
proceed on August 1, 2019. ITS Group employees traveled to Alaska to begin work on the
buildings. After a government âinspector-in-trainingâ took the employees on a walkthrough
of the site, the inspector discussed and identified certain weathered areas (the southern facing
sides of the buildings), noted that the contract required additional preparation and priming
to paint those areas, and provided the contractor with paint samples of the paint colors
specified by the contract. ITS Group began work that afternoon. Over the weekend of
August 10â11, ITS Group painted the exterior of three of the eight buildings with no
oversight by government personnel, who did not remain on the worksite over the weekend.
The inspector returned to the work site on August 12, 2019. After examining the
painting on the first three buildings, the inspector notified the contracting officer and ITS
Group representatives that he did not believe the work conformed with contract requirements
because it appeared that ITS Group failed to adequately prep the walls prior to painting and
that the painting was uneven. Nonetheless, ITS Group contacted the contracting officer to
request an official walk-through of the first three buildings, seeking to receive progress
payments on the work. The contracting officer told them that the contracting officerâs
representative (COR) would be available on August 15.
When the COR arrived on August 15, 2019, it appeared that the paint crew had
departed the worksite and removed its equipment. After inspecting the work on the three
buildings, the COR determined that the contractor had failed to paint the three buildings in
conformance with contract specifications. The COR recommended that the contracting
officer not release a progress payment for the work completed as it was not acceptable.
CBCA 6621, 6747 3
On August 16, the contracting officer sent ITS Group a cure notice as well as a notice
of noncompliance with the terms of the contract. On August 20, the contracting officer sent
ITS Group a revised cure notice which requested that ITS Group provide a plan for redoing
the work to meet contract requirements.
ITS Group responded to the cure notice by asserting that the contractor had rendered
services and should be paid its progress payment for the work performed.