ASBCA 59809
Board: ASBCA
Agency: Army
Appellant: Relyant, LLC
Date: 2018-06-27
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Relyant, LLC ) ASBCA No. 59809
)
Under Contract No. W91B4N-08-D-0011 )
APPEARANCE FOR THE APPELLANT: James H. Price, Esq.
Lacy, Price & Wagner, PC
Knoxville, TN
APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq.
Army Chief Trial Attorney
MAJ Jason W. Allen, JA
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE PROUTY
The dispute before us, 1 which was aired in a three-day hearing, is centered upon
the government's acceptance of certain pre-fabricated relocatable buildings (RLBs) for
use at two different sites in Afghanistan. As will be described in far greater detail
below, different government contracting officer representatives (CORs) at the two
different locations had diverging views regarding whether the RLBs initially provided
by appellant, Relyant, LLC (Relyant), should be permitted under the contract
specifications that applied to both locations. In particular, the RLBs delivered to the
first site passed a First Article Test (FAT) at that site, but were deemed to be out of
compliance with the contract's statement of work (SOW) by the contracting officer
(CO), and were not permitted at the second site. To get around the problem, Relyant
shipped the RLB components first delivered to second site to the first site, where the
local accepting authority (not the CO) apparently turned a blind eye to the RLBs'
failure to comply with the SOW2 ; Relyant then revamped its means of manufacturing
the RLBs to provide RLB components that satisfied the CO (and contract) at the
second site. Yet, despite the equities of the matter superficially weighing in favor of
Relyant for having had some units accepted, we find that we cannot grant it the relief
1
We granted summary judgment in favor of the government in the related appeal of
ASBCA No. 58172. See Relyant, LLC, ASBCA No. 58172, 16-1 BCA ,r 36,228,
aff'd, 683 F. App'x 960 (Fed. Cir. 2017). Citations to the Rule 4 file herein refer
to a single Rule 4 file that was originally submitted for that first appeal and later
supplemented for this one.
2
To be clear, there was only one CO at a time on the contract. As noted, though, there
was more than one COR.
sought. The CO was within her rights to hold Relyant to the specifications contained
within the contract's SOW, and the evidence does not support a finding of superior
knowledge on the part of the government. Moreover, the doctrine of good faith and
fair dealing does not override the express terms of the contract; however, in the
circumstances presented here, it does impose upon the government certain obligations
with regard to timeliness of government responses to Relyant's request to amend the
SOW, for which Relyant is entitled to certain relief. 3
FINDINGS OF FACT
I. The Contract
The idea behind the RLB is rather clever: standard sized steel shipping
containers - ubiquitous in the modem world and designed to be easily transported -
would be modified to be used as modular building blocks to make larger buildings for use
in contingency operations (tr. 1/195-96, 201-04). On 15 May 2008, the Bagram Regional
Contracting Center in Afghanistan (the Army or the government} solicited proposals
for the above-captioned contract (the contract), which was a multiple award,
indefinite-delivery/indefinite-quantity (IDIQ) contract for the manufacture, delivery, and
installation ofRLBs in Afghanistan (R4, tab 1).
The seeds of the dispute that are now before us were sown in Relyant' s4
proposal in response to this solicitation. The SOW accompanying the solicitation for
the contract required the installation of gypsum interior drywall to the interior of
the shipping containers that would cover fiberglass insulation that was a minimum of
three inches thick (R4, tab 1 at 17, 1 4.1.1.1 ). Relyant proposed a different
configuration: this was the use of a sandwich panel, including Styrofoam5 as the
insulator, instead of separate insulation and drywall (R4, tab 243 at 11-12 6 ; see also
tr. 2/124-26). This configuration made all the difference in the world to how Relyant
3 We also resolve a number of motions regarding the entitlement of Relyant to amend
its complaint; the government's entitlement to amend its answer; and whether
an adverse inference should be drawn against the government due to certain
discovery hiccups.