CBCA 4779
Board: CBCA
Agency: Department of Transportation
Appellant: Tucci & Sons, Inc.
Date: 2016-12-20
Outcome: denied
DENIED: December 20, 2016
CBCA 4779
TUCCI & SONS, INC.,
Appellant,
v.
DEPARTMENT OF TRANSPORTATION,
Respondent.
J. Craig Rusk and Alix K. Town of Oles Morrison Rinker & Baker, LLP, Seattle, WA,
counsel for Appellant.
Rayanne L. Speakman, Office of the Chief Counsel, Western Federal Lands Highway
Division, Federal Highway Administration, Department of Transportation, Vancouver, WA,
counsel for Respondent.
Before Board Judges SHERIDAN, WALTERS, and LESTER.
SHERIDAN, Board Judge.
Tucci & Sons, Inc. (Tucci) appeals the final decision of the Department of
Transportation, Federal Highway Administration (FHWA), denying its claim for an equitable
adjustment in the amount of $81,320.45 for increased labor and equipment costs resulting
from alleged differing site conditions encountered in its performance of utility trench work
in Mount Rainier National Park. After a hearing on the merits, we deny the appeal because
Tucci was adequately informed by the contract drawings that it was digging in âundisturbed
native materialâ and that, because of the conditions of the site, it should have anticipated that
it might encounter a variety of different sizes of boulders.
CBCA 4779 2
Background
This appeal arises out a contract to reconstruct a 9.7-mile portion of the roadway in
Mount Rainier National Park from the parkâs Nisqually Entrance to Paradise Valley and
install a utility trench in a 6.06-mile length of the road. The park is located on Mount
Rainier, which is a snow-capped volcano covered by several glaciers. The glaciers erode
materials which travel down the mountain via gravity and rivers as glacial, alluvial, and mud
deposits containing sands, gravel, cobbles, and boulders. Beneath those materials is bedrock,
which sometimes breaches the surface of the deposits. The Board takes judicial notice of
the fact that construction of the Nisqually Entrance to Paradise Valley portion of the roadway
began in 1903 and was completed in 1915. 48 CFR 6101.25(a)(1) (2015); see
http://npshistory.com/publications/highways/mount_rainier/mount-rainier.pdf (an online
park brochure âHighways in Harmony, Mount Rainier Roads and Bridgesâ that was last
visited Dec. 16, 2016). The road from Nisqually Entrance to Paradise Valley was one of the
first roads built in a national park.
A. Solicitation
In 2013, the FHWAâs Western Federal Lands Highway Division (WFLHD) solicited
bids for the reconstruction of portions of the roadway from Nisqually Entrance to Paradise
Road and construction of utility trenches within portions of that road. The utility trench
work was to be performed on the left-hand side of the downhill lane of the two-lane
roadway, the lane that was closer to the mountain.1
The length of the project spanned approximately 32,700 linear feet, beginning at
station 25+80 and ending at station 346+00.2 The project drawings detailed four types of
utility trenches that the contractor potentially would be constructing for the conduit
installation (Types A, B, C, and D), but the contract generally specified the use of the Type
A trench. Use of the Type A trench required the contractor to excavate an area two feet
wide (24") by three-and-a-half feet deep (42") and to install conduit at a depth of three feet
(36"). In pertinent part, drawing K-8, âUTILITY TRENCH TYPE A,â showed âundisturbed
native materialâ outside the trenches, with the Type A trench being backfilled with
approximately twenty inches of bedding material, six inches of backfill material, and four
1
The project was along the Nisqually River, which originates at the Nisqually
Glacier, one of the main glacial drainages on Mount Rainier.
2
The station numbers denote the trenchâs distance in feet from the beginning of
Nisqually Road (station 0+00). Thus, the trenching began 2580 feet from the start of the road
and ended a distance of 34,600 feet away from the entrance.
CBCA 4779 3
inches of aggregate base, and then paved with five inches of minor hot asphalt concrete.
The plans for the three other types of trenches similarly showed âundisturbed native
materialâ outside the trenches, and varying amounts of bedding, backfill, and other materials
covering the cables which was then covered by four inches of aggregate base, and paved
with five inches of minor hot asphalt concrete.