CBCA 4601
Board: CBCA
Appellant: Charles Blalock and Sons, Inc.
Date: 2015-07-21
Outcome: denied
DENIED: July 21, 2015
CBCA 4601
CHARLES BLALOCK AND SONS, INC.,
Appellant,
v.
DEPARTMENT OF TRANSPORTATION,
Respondent.
Philip E. Beck and Daniel J. Greenberg of Smith Currie & Hancock LLP, Atlanta,
GA, counsel for Appellant.
Rayann L. Speakman, Office of the Chief Counsel, Federal Highway Administration,
Department of Transportation, Vancouver, WA, counsel for Respondent.
SHERIDAN, Board Judge.
This dispute involves a contract between the Department of Transportation’s Federal
Highway Administration (FHWA) and Charles Blalock and Sons, Inc. (Blalock), to
rehabilitate the Gatlinburg Bypass and Newfound Gap Road in the Great Smoky Mountains
National Park in Tennessee. The contract included a number of line items, each with an
estimated quantity and a unit price. After award, one of the line items was deleted and the
contract price was consequently reduced. Blalock asserts that by eliminating the work, the
FHWA improperly deprived it of the portion of its home office overhead that would have
been absorbed by that line item. The amount in dispute is $23,708.37.
Blalock elected to have this appeal processed under the Board’s expedited procedure
for small claims. Rule 52 (48 CFR 6101.52 (2014)). This rule permits issuance of a decision
in summary form. Decisions issued under the small claims procedure are final and
conclusive and shall not be set aside except in cases of fraud affecting the Board’s
CBCA 4601 2
proceedings. 41 U.S.C. § 7106(b) (2012); Palmer v. Barram, 184 F.3d 1373 (Fed. Cir.
1999). This decision has no value as precedent. The parties also elected to have the appeal
processed under Board Rule 19, Submission on the Record Without a Hearing, and each
submitted briefs and relevant documents which have been admitted into the record. 48 CFR
6101.19.
Background
The contract, which was awarded in August 2013, specified that it was “for the
quantities of work actually performed at the unit prices as bid in the Bid Schedule.” One of
the line items, A0910, was described as “hot asphalt concrete pavement, Marshall test, class
A, grading E, wedge or leveling course.” The estimated quantity for this item was 2900 tons.
In the bid schedule, Blalock bid this item at $140 per ton, for a total amount of $406,000.
Shortly after award, the FHWA determined that none of the line item A0910 work was
necessary. The parties later executed a contract modification which, among other things,
provided that this work was deleted and the contract price was reduced. Blalock claims that
the reduction was excessive.
The parties disagree as to which contract clause should be applied to determine the
reduction in contract price as a consequence of the elimination of line item A0910. Blalock
points to the Variation in Estimated Quantity (VEQ) clause, Federal Acquisition Regulation
(FAR) 52.211-18, which provides, in pertinent part:
If the quantity of a unit-priced item in this contract is an estimated quantity and
the actual quantity of the unit-priced item varies more than 15 percent above
or below the estimated quantity, an equitable adjustment in the contract price
shall be made upon demand of either party. The equitable adjustment shall be
based upon any increase or decrease in costs due solely to the variation above
115 percent or below 85 percent of the estimated quantity.
48 CFR 52.211-18 (2012).
FHWA believes that the applicable contract clause is section 109.07 of the Standard
Specifications for Construction of Roads and Bridges on Federal Highway Projects, which
is entitled “Eliminated Work.” This clause states:
CBCA 4601 3
Follow the requirements of FAR Clause 52.243-4 Changes.[1]
Work may be eliminated from the contract without invalidating the contract.
The Contractor is entitled to compensation for all direct costs incurred before
the date of elimination of work plus profit and overhead on the direct incurred
costs. Anticipated profit and overhead expense on the eliminated work will
not be compensated.
Discussion
Resolving this dispute calls for us to follow basic rules of contract interpretation:
When interpreting the contract, the document must be considered as a whole
and interpreted so as to harmonize and give reasonable meaning to all of its
parts. McAbee Constr., Inc. v.