CBCA 5683
Board: CBCA
Agency: Department of State
Appellant: Pernix Serka Joint Venture
Date: 2020-04-22
Outcome: denied
DENIED: April 22, 2020
CBCA 5683
PERNIX SERKA JOINT VENTURE,
Appellant,
v.
DEPARTMENT OF STATE,
Respondent.
J. Randolph MacPherson of Halloran & Sage LLP, Washington, DC; and Douglas L.
Patin of Bradley Arant Boult Cummings, Washington, DC, counsel for Appellant.
Erin M. Kriynovich, Office of the Legal Adviser, Buildings and Acquisitions,
Department of State, Rosslyn, VA, counsel for Respondent.
Before Board Judges SOMERS (Chair), VERGILIO, and SHERIDAN.
SOMERS, Board Judge.
Appellant, Pernix Serka Joint Venture (PSJV), faced with concerns about performing
a contract in Freetown, Sierra Leone, during an Ebola virus disease (Ebola) outbreak, sought
guidance from the Department of State (DOS) contracting officer as to how to respond. DOS
provided no guidance, stating that PSJV would need to make its own decisions about the
process for completing contract performance under such conditions. PSJV temporarily
demobilized, later returning to the site having contracted for additional medical services for
its employees. After contract completion, PSJV requested an equitable adjustment for costs
incurred. DOS moves for summary judgment on the grounds that the risk of performance
in this firm, fixed-price contract remained with PSJV PSJV has identified no genuine issues
CBCA 5683 2
of material fact, and DOS is entitled to prevail as a matter of law. After considering the
motion, opposition, and reply, we grant DOSâs motion and deny the appeal.
Statement of Facts
In September 2013, DOS awarded a firm, fixed-price contract in the amount of
$10,864,047 to PSJV. The contract required PSJV to construct a rainwater capture and
storage system in Freetown, Sierra Leone. The initial price included all labor, materials,
equipment, and services necessary to complete the project. In addition to the fixed-price
sum, the contract limited additional reimbursement for value added taxes, not to exceed
$1,626,195. The contract included a clause entitled âExcusable Delays,â which stated:
F.8.1 The Contractor will be allowed time, not money, for excusable delays
as defined in FAR 52.249-10, Default (see Section/Paragraph I.153).
Examples of such cases include (1) acts of God or of the public enemy; (2) acts
of the United States Government in either its sovereign or contractual capacity;
(3) acts of the government of the host country in its sovereign capacity; (4) acts
of another contractor in the performance of a contract with the Government;
(5) fires; (6) floods; (7) epidemics; (8) quarantine restrictions; (9) strikes; (10)
freight embargoes; and (11) unusually severe weather.
F.8.2 In each instance, the failure to perform must be beyond the contract and
without the fault or negligence of the Contractor, and the failure to perform
furthermore (1) must be one that the Contractor could not have reasonably
anticipated and taken adequate measures to protect against, (2) cannot be
overcome by reasonable efforts to reschedule the work, and (3) directly and
materially affects the date of final completion of the project.
DOS issued a notice to proceed to PSJV on December 17, 2013. The contract
required PSJV to complete the project within 335 calendar days, with a completion date of
November 17, 2014. PSJV began performance, completing sixty-five percent of the project
by August 7, 2014.
An outbreak of the Ebola virus began in the Republic of Guinea in March 2014.
Ebola spread to Freetown, Sierra Leone, by July 2014. PSJV became concerned about the
potential impact of the spread of the virus and the ability to support contractor personnel
should they need to be evacuated. In an email to the contracting officer on July 31, 2014,
PSJV sought âinstructions on the way forward.â On August 6, 2014, PSJV told the
contracting officer that âwe do not want to act unilaterally and need to have a discussion with
CBCA 5683 3
you, get directions, or at least a consensus of the right action of the way forward.â The
contracting officer responded via email on August 6:
I just got off the phone with Najib Mahmood [the Africa Branch Chief for the
Bureau of Overseas Operations (OBO), a branch within DOS] and understand
that the Post has NOT issued an ordered departure for the Embassy at the
present time.