CBCA 5683

Board: CBCA Agency: Department of State Appellant: Pernix Serka Joint Venture Date: 2020-04-22 Outcome: denied
View full appeal with AI analysis on ProtestIntel →
DENIED: April 22, 2020 CBCA 5683 PERNIX SERKA JOINT VENTURE, Appellant, v. DEPARTMENT OF STATE, Respondent. J. Randolph MacPherson of Halloran & Sage LLP, Washington, DC; and Douglas L. Patin of Bradley Arant Boult Cummings, Washington, DC, counsel for Appellant. Erin M. Kriynovich, Office of the Legal Adviser, Buildings and Acquisitions, Department of State, Rosslyn, VA, counsel for Respondent. Before Board Judges SOMERS (Chair), VERGILIO, and SHERIDAN. SOMERS, Board Judge. Appellant, Pernix Serka Joint Venture (PSJV), faced with concerns about performing a contract in Freetown, Sierra Leone, during an Ebola virus disease (Ebola) outbreak, sought guidance from the Department of State (DOS) contracting officer as to how to respond. DOS provided no guidance, stating that PSJV would need to make its own decisions about the process for completing contract performance under such conditions. PSJV temporarily demobilized, later returning to the site having contracted for additional medical services for its employees. After contract completion, PSJV requested an equitable adjustment for costs incurred. DOS moves for summary judgment on the grounds that the risk of performance in this firm, fixed-price contract remained with PSJV PSJV has identified no genuine issues CBCA 5683 2 of material fact, and DOS is entitled to prevail as a matter of law. After considering the motion, opposition, and reply, we grant DOS’s motion and deny the appeal. Statement of Facts In September 2013, DOS awarded a firm, fixed-price contract in the amount of $10,864,047 to PSJV. The contract required PSJV to construct a rainwater capture and storage system in Freetown, Sierra Leone. The initial price included all labor, materials, equipment, and services necessary to complete the project. In addition to the fixed-price sum, the contract limited additional reimbursement for value added taxes, not to exceed $1,626,195. The contract included a clause entitled “Excusable Delays,” which stated: F.8.1 The Contractor will be allowed time, not money, for excusable delays as defined in FAR 52.249-10, Default (see Section/Paragraph I.153). Examples of such cases include (1) acts of God or of the public enemy; (2) acts of the United States Government in either its sovereign or contractual capacity; (3) acts of the government of the host country in its sovereign capacity; (4) acts of another contractor in the performance of a contract with the Government; (5) fires; (6) floods; (7) epidemics; (8) quarantine restrictions; (9) strikes; (10) freight embargoes; and (11) unusually severe weather. F.8.2 In each instance, the failure to perform must be beyond the contract and without the fault or negligence of the Contractor, and the failure to perform furthermore (1) must be one that the Contractor could not have reasonably anticipated and taken adequate measures to protect against, (2) cannot be overcome by reasonable efforts to reschedule the work, and (3) directly and materially affects the date of final completion of the project. DOS issued a notice to proceed to PSJV on December 17, 2013. The contract required PSJV to complete the project within 335 calendar days, with a completion date of November 17, 2014. PSJV began performance, completing sixty-five percent of the project by August 7, 2014. An outbreak of the Ebola virus began in the Republic of Guinea in March 2014. Ebola spread to Freetown, Sierra Leone, by July 2014. PSJV became concerned about the potential impact of the spread of the virus and the ability to support contractor personnel should they need to be evacuated. In an email to the contracting officer on July 31, 2014, PSJV sought “instructions on the way forward.” On August 6, 2014, PSJV told the contracting officer that “we do not want to act unilaterally and need to have a discussion with CBCA 5683 3 you, get directions, or at least a consensus of the right action of the way forward.” The contracting officer responded via email on August 6: I just got off the phone with Najib Mahmood [the Africa Branch Chief for the Bureau of Overseas Operations (OBO), a branch within DOS] and understand that the Post has NOT issued an ordered departure for the Embassy at the present time.