ASBCA 63240
Board: ASBCA
Agency: Navy
Appellant: KUNJ Construction Corporation
Date: 2024-01-25
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
KUNJ Construction Corporation ) ASBCA No. 63240
)
Under Contract No. N40085-16-D-0302 )
APPEARANCES FOR THE APPELLANT: Matthew T. Schoonover, Esq.
John M. Mattox II, Esq.
Timothy J. Laughlin, Esq.
Schoonover & Moriarty LLC
Olathe, KS
APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq.
Navy Chief Trial Attorney
Merideth Mendenhall, Esq.
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE MCLISH ON
THE PARTIESâ CROSS-MOTIONS FOR SUMMARY JUDGMENT
This appeal involves a contract to replace a central base fire system at the
Philadelphia Naval Business Center in Philadelphia, Pennsylvania. The Navy moves
for summary judgment on the grounds that the undisputed facts establish that the
claims asserted by appellant KUNJ Construction Corporation (KUNJ) are barred by
the Navyâs affirmative defenses of accord and satisfaction and release, and also that
the claims lack merit. KUNJ cross-moves for summary judgment in its favor on the
governmentâs affirmative defenses and contests the Navyâs position that it is entitled to
summary judgment on the merits of the claims.
We deny the motions.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
In accordance with Board Rule 7(c)(1), the government included with its
motion a Statement of Undisputed Material Facts (NSUMF), with which KUNJ raises
no material dispute (app. resp. at 2). KUNJâs opposition and cross-motion provided a
Statement of Further Undisputed Material Facts (KFUMF) (id. at 2-6). The
government objects to many of these as legal conclusions or irrelevant but does not
dispute their factual content (Navy resp. to KFUMF at 3-10). Below, we summarize
the facts that neither party disputes for purposes of these motions.
The Contract and Task Order
1. On or about December 7, 2015, the Navy and KUNJ entered into Contract
No. N40085-16-D-0302, a firm-fixed price, multiple-award construction contract for
âNew Construction, Renovation, Alteration and Repair Projects primarily in the state
of Pennsylvaniaâ (Contract) (NSUMF ¶ 1; R4, tab 1 at GOV000001-77).
2. On or about August 2, 2016, the Navy awarded KUNJ Task Order 0004
(Task Order 4), a firm fixed-price task order under the Contract, to âReplace the
Central Base Fire System @ [Philadelphia Naval Business Center] PNBC Phila. PA,â
in the total amount of $2,449,000 (NSUMF ¶ 5; compl. at ¶ 6; R4, tab 6
at GOV000089-105).
3. Task Order 4 required KUNJ to âinstall a new base radio fire monitoring
system and install a fire alarm system in buildings 20 & 1029â (NSUMF ¶ 6; R4, tab 6
at GOV000091).
4. The original contract completion date for Task Order 4 was August 1, 2018
(NSUMF ¶ 7; KFUMF ¶ 63; R4, tab 6 at GOV000098).
Modification No. P0001
5. KUNJ and the Navy entered into bilateral Modification No. P0001
(Modification No. 1) to Task Order 4 with an effective date of August 20, 2018.
Modification No. 1 was a no-cost modification that extended the completion date to
June 14, 2019, and changed various technical aspects of Task Order 4, including
installation of transmitters, dialers, master boxes, strobe lights, roving photovoltaic
transmitters, and removal of existing transmitters, disconnect switches, and notification
devices (NSUMF ¶ 20; KFUMF ¶ 50; R4, tab 7 at GOV000393-94). Several of the
technical changes included work in Buildings 20 and 1029 (NSUMF ¶ 20; R4, tab 7 at
GOV000393).
6. Modification No. 1 was executed by both parties as of August 22, 2018
(NSUMF ¶¶ 21-22; govât reply at 2; 1 R4, tab 7 at GOV000392).
1
The Navyâs Reply in Support of its Motion for Summary Judgment and Response in
Opposition to KUNJâs Cross-Motion is unpaginated. We refer to the page
numbers shown in the pdf file containing the document.
2
7. Modification No. 1 included the following language:
Acceptance of this modification by the Contractor
constitutes an accord and satisfaction and represents
payment in full for both time and money and for any and
all costs, impact effect, and for delays and disruptions
arising out of, or incidental to, the work as herein revised.
(NSUMF ¶ 23; R4, tab 7 at GOV000393)
Modification No. P0002
8.