ASBCA 63710
Board: ASBCA
Agency: Air Force
Appellant: NES Pacific Limited Liability Co.
Date: 2025-09-02
Outcome: sustained
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
NES Pacific Limited Liability Co. ) ASBCA No. 63710-ADR
)
Under Contract No. FA5270-17-D-0012 )
Task Order No. FA52700-17-F-0098 )
APPEARANCE FOR THE APPELLANT: David A. Rose, Esq.
Rose Consulting Law Firm
Valdosta, GA
APPEARANCES FOR THE GOVERNMENT: Caryl A. Potter, III, Esq.
Air Force Deputy Chief Trial Attorney
LeâDara Clark, Esq.
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE ARNETT
By agreement dated February 26, 2025, the parties elected to have this matter
considered and decided through a summary proceeding with binding decision pursuant
to the Boardâs Alternative Dispute Resolution (ADR) procedures. The parties have
agreed that the Boardâs decision on entitlement will be final, conclusive, not
appealable, and may not be set aside except for fraud. This decision will have no
precedential value.
Appellant NES Pacific Limited Liability Co. (NESP) seeks compensation for
two interrelated issues: 1) switchgear 1 that were ordered timely, manufactured to meet
contract specifications/drawings, delayed as a result of a labor shortage due to
COVID-19, shipped from the U.S., delivered to the project at Kadena Air Base, Japan
approximately 16 days after the contract completion date (CCD), and refused by the
Air Force; and 2) storage/demurrage charges, continuing to accrue daily, arising from
the governmentâs refusal to accept the late switchgear.
The Air Force contends that, through bilateral Modification No. P00008, NESP
released its claim for any subcontractor delay giving rise to the late delivery and
associated costs.
1
Since quantum is not before the Board, this decision does not address the claimed costs.
However, if NESPâs claim includes costs for the price adjustment sought by Eaton due
to COVID-19 market price fluctuation, such costs are not recoverable because the
parties entered into a firm fixed price contract, and that risk is borne by NESP.
The Board carefully considered the documents in the Rule 4 file, exhibits, and
the contentions of the parties in the pleadings and briefs.
DECISION
It is the decision of the Board that, on this construction contract, the
governmentâs rejection of the switchgear was improper. The rejection appears to have
been based solely on a late delivery caused by labor shortages resulting from COVID-
19. The contract included Federal Acquisition Regulation (FAR) clause 52.249-10,
Default (Fixed-Price Construction) (R4, tab 1 at 17). A manufacturing delay arising
from a labor shortage during a global pandemic is the type of delay commonly
addressed by the Default Clause as beyond the control and without the fault or
negligence of the contractor and subcontractor. 2
Further, it is the decision of the Board that NESP did not release its claim under
Modification No. P00008. Issued five months prior to NESPâs late delivery of the
switchgear, the modification granted a time extension and directed NESP to complete
work to âcorrect unsafe and incomplete above ground work locationsâ as described in
a supplement to the Scope of Work (SOW) (R4, tab 3 at 2). However, the
modification does not provide any information regarding the basis for the time
extension or attach the supplement (id.). The release is limited to the âfacts or
circumstances giving rise to the SOW changes identifiedâ which cannot be discerned
from reading the modification (id.). Thus, Modification No. P00008 provides
insufficient information for us to conclude that it operates as a release of NESPâs
claim.
CONCLUSION
Therefore, the appeal is sustained. The matter is returned to the parties for the
resolution of quantum.
Dated: September 2, 2025
LAURA J.