ASBCA 60649
Board: ASBCA
Agency: U.S. Army Engineer District
Appellant: Areyana Group of Construction Company
Date: 2018-10-15
Outcome: dismissed
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of-- )
)
Areyana Group of Construction Company ) ASBCA No. 60649
)
Under Contract No. W5J9LE-12-C-0044 )
APPEARANCE FOR THE APPELLANT: Mr. Zabit Khan
Director
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
James D. Stephens, Esq.
Engineer Trial Attorney
U.S. Army Engineer District, Middle East
Winchester, VA
Edward J. McNaughton, Esq.
Engineer Trial Attorney
U.S. Army Engineer District, Memphis
OPINION BY ADMINISTRATIVE JUDGE PAUL
ON JURISDICTION
This is a timely appeal of a contracting officer's final decision (COFD) denying
appellant Areyana Group of Construction Company's (AGCC's) request for a no-cost
time extension, as well as additional costs for construction of a groundwater storage
tank. The Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, is applicable.
Pursuant to an order dated May 17, 2018, the Board instructed the parties to brief the
issue of the Board's jurisdiction; only the government responded to our order. 1
FINDINGS OF FACT
1. On May 28, 2012, the government entered into a fixed-price contract,
No. W5J9LE-12-C-0044, with AGCC in a total amount of$4,754,40I.51 (R4, tab 7
at 1-2 of 47). As stated in the contract:
1
This appeal was consolidated with ASBCA No. 60648. We promulgated a decision
dismissing that appeal on May 11, 2018. Areyana Group a/Construction Co.,
ASBCA No. 60648, 18-1 BCA ,i 37,050. Familiarity with that decision is
·presumed.
f
This project consists of the design and construction
of site improvements and construction of facilities to
support the Afghanistan National Police (ANP) program
for one ( 1) Provincial Response Company (PRC)
compound serving a population of approximately one
hundred thirty-one (131) personnel, to be located in
Lashkar Gah, Helmand, Province, Afghanistan. This
project is defined as the management, planning, design,
material, labor, and equipment, to site adapt and construct
all utilities, vehicular access, buildings, force protection
measures, site security, mine clearance activities, and other
features as required herein.
(Id. at 6 of 47)
2. The contract incorporated by reference several Federal Acquisition
Regulation (FAR) clauses, including FAR 52.233-1, DISPUTES (JUL 2002) (id. at 8 of
4 7), which stated, in pertinent part:
(c) Claim, as used in this clause, means a written
demand or written assertion by one of the contracting
parties seeking, as a matter of right, the payment of money
in a sum certain, the adjustment or interpretation of
contract terms, or other relief arising under or relating to
this contract. However, a written demand or written
assertion by the Contractor seeking the payment of money
exceeding $100,000 is not a claim under the [CDA] until
certified.
3. The contract contained FAR 52.211-12, LIQUIDATED DAMAGES-CONSTRUCTION
(SEP 2000), which provided for damages in the amount of $1,301.00 for each day of delay in
completing the work. In addition, the contract included FAR 52.211-10, COMMENCEMENT,
PROSECUTION, AND COMPLETION OF WORK (APR 1984), which stated:
The Contractor shall be required to (a) commence work
under this contract within Ten (10) calendar days after the
date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and (c) complete the
entire work ready for use not later than Three hundred
Sixty-five (365) calendar days after Notice to Proceed
2
(NTP). The time stated for completion shall include final
cleanup of the premises.
(R4, tab 7 at 44-45 of 47)
4.