ASBCA 62936
Board: ASBCA
Agency: Army Corps of Engineers
Appellant: JE Dunn Construction Co.
Date: 2022-04-25
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
JE Dunn Construction Co. ) ASBCA No. 62936
)
Under Contract No. W9127S-17-D-6003 )
APPEARANCES FOR THE APPELLANT: Reginald M. Jones, Esq.
David Timm, Esq.
Nicholas T. Solosky, Esq.
Fox Rothschild LLP
Washington, DC
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Michael T. Geiselhart, Esq.
Liz K. Harris, Esq.
Engineer Trial Attorneys
U.S. Army Engineer District, Little Rock
OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD
PURSUANT TO RULE 12.3
This appeal involves a contract for JE Dunn Construction Company (JE Dunn) to
perform design-build construction work for the United States Army Corps of Engineers
(USACE or government) at Fort Drum, New York. JE Dunn alleges that USACE changed
the contract by implementing COVID-19-related restrictions requiring all personnel
arriving at Fort Drum from more than 350 miles away to quarantine for 14 days prior to
performing work on-site. USACE argues that the sovereign acts doctrine bars JE Dunnâs
claim, that JE Dunn would still have been required to quarantine under New Yorkâs
COVID-19 protocols and therefore would have suffered the same damages
notwithstanding Fort Drumâs quarantine requirement, and that the risk of costs relating to
a pandemic or quarantine under a fixed-price contract rest with the contractor. The Board
has jurisdiction over this appeal pursuant to the Contract Disputes Act of 1978, 41 U.S.C.
§§ 7101-7109. JE Dunn elected Rule 12.3 disposition, and both parties elected to submit
this appeal on the record pursuant to Board Rule 11. We deny the appeal.
FINDINGS OF FACT
1. On July 14, 2017, USACE awarded Contract No. W9127S-17-D-6003 (the
contract) to JE Dunn for design-build construction work (R4, tab 1 at 1 1).
1
Page number citations refer to the PDF page number, unless otherwise stated.
2. On September 25, 2018, USACE awarded Task Order No. W9127S-18-F-0155
to JE Dunn under the contract. This task order was for heating, ventilation, and air
conditioning (HVAC) replacement services at the Guthrie Health Care Clinic at Fort
Drum at a total price of $30,428,439. (R4, tab 2 at 46-51)
3. The contract incorporated by reference Federal Acquisition Regulation (FAR)
52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (Default
Clause) (R4, tab 1 at 9). This clause provides, in part:
(b) The Contractor's right to proceed shall not be terminated
nor the Contractor charged with damages under this clause,
ifâ
(1) The delay in completing the work arises from
unforeseeable causes beyond the control and without the fault
or negligence of the Contractor. Examples of such causes
include . . .
(vi) epidemics
(vii) quarantine restrictions . . . .
(2) The Contractor, within 10 days from the beginning of any
delay (unless extended by the Contracting Officer), notifies
the Contracting Officer in writing of the causes of delay. The
Contracting Officer shall ascertain the facts and the extent of
delay. If, in the judgment of the Contracting Officer, the
findings of fact warrant such action, the time for completing
the work shall be extended.
FAR 52.249-10(b)(1-2)
4. On April 22, 2020, Major General Brian Mennes, the Fort Drum Commander,
imposed General Order No. 1B. This orderâwhich applied to service members, their
dependents, and civilian personnelâoutlined prevention and mitigation procedures
aimed at slowing the spread of COVID-19. (R4, tab 3 at 102-09)
5. By letter dated May 4, 2020, JE Dunn notified USACE of pandemic-related on-
site health and cleaning changes that would increase the cost of performance and cause
delays. These changes included conditional or limited jobsite access. (R4, tab 4 at 110)
6.