CBCA 4078
Board: CBCA
Agency: Department of Veterans Affairs
Appellant: Affliated Western, Inc.
Date: 2017-07-24
Outcome: denied
DENIED: July 24, 2017
CBCA 4078
AFFILIATED WESTERN, INC.,
Appellant,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
Paul H. Sanderford of Sanderford & Carroll, P.C., Temple, TX, counsel for Appellant.
Mary A. Mitchell, Office of General Counsel, Department of Veterans Affairs,
Houston, TX, counsel for Respondent.
Before Board Judges SOMERS, HYATT, and GOODMAN.
SOMERS, Board Judge.
Affiliated Western, Inc. (AWI or appellant) appeals the final decision by a contracting
officer for the Department of Veterans Affairs (VA, respondent , or Government) terminating
for default AWI’s contract for the renovation of the surgical unit at the Oscar G. Johnson VA
Medical Center in Iron Mountain, Michigan. AWI seeks conversion of the termination for
default to a termination for convenience. For the reasons explained below, we sustain the
VA’s termination for default and deny the appeal.
CBCA 4078 2
Background
I. The Solicitation
On March 27, 2013, the Government issued a solicitation for the renovation of a
19,400 square foot surgery unit and 705 square foot mechanical room at the Oscar G.
Johnson VA Medical Center in Iron Mountain, Michigan. On April 10, 2013, the VA
conducted a pre-bid site visit of the medical facility for interested bidders. The parties
disagree on whether AWI attended this site visit.
On April 23, 2013, the Government amended the solicitation through amendment
A00006 (amendment) and warned prospective bidders that the schedule for the project “is
very aggressive” and involves “a very important department to the facility.” The amendment
provided a phasing plan, requiring that the contractor complete the project in 400 days. Due
to the impact on the medical center, the amendment emphasized the importance of
maintaining the projected contract schedule. The amendment allotted each phase of the
project the following durations:
Mobilization/Submittals – 12 weeks
Phase 1 – 14 weeks
Phase 2 – 2 weeks
Owner moving between phases 2 & 3 – 2 weeks
Phase 3 – 18 weeks
Owner moving between phases 3 & 4 – 2 weeks
Phase 4 – 4 weeks
Phases 0 and 5 work ongoing throughout project duration
Further, the amendment required that “[a]ny changes to this schedule shall be approved
through the contracting office and justified through the approved CPM [critical path method]
project schedule.”
Phase 1 required vacating the dental suite and relocating the ambulatory surgery wing
to provide space for the contractor during the duration of the project. Phase 2 involved
rerouting a corridor to allow for use of the vacated areas in phase 1 after the contractor
finished phases 1 and 2. Phase 3, the most significant part of the project, involved the
renovation of the operating rooms and the removal of the hospital roof to facilitate the
installation of medical equipment. Phase 4 required the contractor to convert the phase 1
areas back into an ambulatory surgery wing. Phase 5 involved finishing the corridor and
elevator lobby. Lastly, phase 0 involved site work to the mechanical room. The solicitation
CBCA 4078 3
called for phases 1 through 4 to be completed sequentially. Phases 0 and 5 could be
performed throughout the duration of the project.
II.