CBCA 4452
Board: CBCA
Appellant: Rodriguez Construction LLC
Date: 2016-04-22
GRANTED IN PART: April 22, 2016
CBCA 4452
RODRIGUEZ CONSTRUCTION LLC,
Appellant,
v.
GENERAL SERVICES ADMINISTRATION,
Respondent.
Manuel Rodriguez, Principal of Rodriguez Construction LLC, Denver, CO, appearing
for Appellant.
Leigh Ann Bunetta, Office of Regional Counsel, General Services Administration,
Denver, CO, counsel for Respondent.
Before Board Judges VERGILIO, KULLBERG, and WALTERS.
VERGILIO, Board Judge.
On January 16, 2015, the Board received from Rodriguez Construction LLC
(contractor) a notice of appeal arising under its contract with the General Services
Administration (agency) under which the contractor performed work on a retention pond at
the Denver Federal Center in Colorado. The contractor disputes a contracting officerâs denial
of its claim to recover $42,859.31 (for what the contractor deems to be an increase due for
work deleted from the contract, $4179.80; additional work, $10,510.95; and completed, but
unpaid work, $28,168.56), as well as the agencyâs reduction in the contract price for deleted
work ($13,445.51) and the agencyâs assessment of liquidated damages ($18,740.86). In its
complaint, the contractor contends it is owed $47,704.51, which is the sum of $37,193.56
(the unpaid contract balance) and $10,510.95 (for alleged additional work).
CBCA 4452 2
The Board concludes that (1) for work deleted from the contract, the contractor is not
entitled to a contract price increase; instead the contract price should be reduced by
$14,561.86; (2) the agency did not alter requirements for swale or security grates, such that
the contractor is not entitled to additional payment; (3) the contractor is liable for $3433.44
in liquidated damages under the contract for delayed substantial completion; and (4) the
contractor is entitled to the unpaid balance on the contract price, $37,193.56, reduced for the
deleted work and liquidated damages.
Accordingly, the Board grants in part the appeal. The contractor is to recover
$19,198.26, with statutory interest to run from August 14, 2014, the date on which the
contractor identified a sum certain for its claim to the contracting officer.
Findings of Fact
The Contract
1. Under the contract, GS-08P-13-JA-P-0043, the contractor was to renovate
detention pond three at the Denver Federal Center, Lakewood, Colorado. Exhibit 4 at 1-3
(all exhibits are in the appeal file, with those submitted by the contractor having a prefix of
âC-â before the number). The contractor was obligated to provide all services and materials
necessary for the proper execution of the work under the contract for the fixed, lump sum
price of $87,100. Exhibit 4 at 3, 6.
2. The scope of work required the contractor to perform various tasks including
demolition, improvements, construction, erosion control, grading, and providing drawings
in AutoCAD format. The contractor was to construct a conventional drain swale as
prescribed in contract drawings and contract documents. While the contract referenced
drawing details for both a conventional swale and an infiltration swale, the agency did not
opt for the infiltration swale; that is, the contract required the contractor to construct a
conventional swale. Exhibits 4 at 57 & 336-39, 49. The original planned schedule of work
identified the conventional (not infiltration) drain swale as a task to be performed. Exhibit
C-1 at 2 (item 16).
3.