ASBCA 62281
Board: ASBCA
Agency: U.S. Army Corps of Engineers
Appellant: Granite Construction Company
Date: 2023-11-01
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Granite Construction Company ) ASBCA No. 62281
)
Under Contract No. W9126G-15-C-0037 )
APPEARANCES FOR THE APPELLANT: Michael A. Branca, Esq.
Joseph N. Frost, Esq.
Peckar & Abramson, P.C.
Washington, DC
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Clark Bartee, Esq.
Engineer Trial Attorney
U.S. Army Engineer District, Galveston
OPINION BY ADMINISTRATIVE JUDGE EYESTER
PURSUANT TO BOARD RULE 11
Granite Construction Company (Granite) appeals a decision by the U.S. Army
Corps of Engineers (Corps or government) denying Granite compensation for 19 days
of a 49-day suspension of work. The Corps concluded that those 19 days were adverse
weather delays, which Granite should have anticipated pursuant to the terms of the
contract. The Board previously granted Granite partial summary judgment on a
contract interpretation issue concerning the interplay of the contract’s unusually severe
weather, default, and suspension of work clauses. According to the decision, the only
remaining issue for the Board to decide is whether the Corps suspended the work for a
reasonable period of time pursuant to the suspension of work clause.
The Board has jurisdiction over the appeal pursuant to the Contract Disputes
Act, 41 U.S.C. § 7101. The parties elected to waive a hearing and submit the
remaining issue in this appeal on the record pursuant to Board Rule 11. Based on the
following, we conclude that the Corps’ suspension of work for 49 days was reasonable
and deny Granite’s appeal.
FINDINGS OF FACT
1. On August 31, 2015, the Corps awarded Granite fixed-priced contract
No. W9126G-15-C-0037 to perform the construction of new outlet structures and
cutoff walls at the Addicks and Barker dams to support the Buffalo Bayou and
Tributaries federal flood control project in Houston, Texas (Joint Stipulations of Fact
(JSF) ¶ 1; R4, tab 1 at 2574, 2628). 1 The contract incorporated by reference Federal
Acquisition Regulation (FAR) 52.242-14, SUSPENSION OF WORK (APR 1984) and
FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (R4,
tab 1 at 2575).
2. In addition, the contract included SECTION 01 10 00.00 45, Part 1.4, TIME
EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (31 OCT 1989)
(ER 415-1-15), which explained how to determine time extensions for unusually
severe weather (more severe than the adverse weather anticipated for the project
location during any given month) in accordance with the default clause. Part 1.4
included a table showing monthly anticipated adverse weather delays and Granite was
required to reflect those delays in its project schedule. For example, the table showed
anticipated adverse weather delays (based on a seven-day work week) for the months
of August (10), September (13) and October (10), for a combined total of 33 days for
those months. The contract also required Granite to record any adverse weather and
resulting impact to normally scheduled work on its daily contractor quality control
reports. If the actual adverse weather delay days exceeded the number of days
anticipated in the schedule, the contracting officer was to convert qualifying delays to
calendar days and issue a modification in accordance with the default clause. (R4,
tab 1 at 2633)
3. In addition, the contract addressed the release of water from the dams.
Specifically, Section 01 00 10, Part 1.4 explained that “under normal conditions” the
operational, combined release of water from the Addicks and Barker dams was limited
to 2,000 cubic feet per second (CFS) as measured downstream at the Piney Point
gauging station (JSF ¶ 4; R4, tab 1 at 2628-29). Section 00 31 33, Paragraph 2.3 of the
contract similarly provided that the combined releases could not exceed 2,000 CFS
“under normal operating conditions” and that the maximum discharge from one reservoir
of 2,000 CFS required the other to be closed (JSF ¶ 5; R4, tab 1 at 2536, 2545).
Part 1.4.1 addressed emergency operations at the dams (R4, tab 1 at 2629). The contract
explained that when emergency scheduled releases were in effect, releases could reach
8,000 CFS for each dam (id. at 2544).
4. On September 29, 2015, the Corps issued, and Granite acknowledged, a
Notice to Proceed.