CBCA 3764
Board: CBCA
Appellant: Klamath Wildlife Resources
Date: 2016-03-31
DENIED: March 31, 2016
CBCA 3764
KLAMATH WILDLIFE RESOURCES,
Appellant,
v.
DEPARTMENT OF THE INTERIOR,
Respondent.
Brian Shaw, Owner of Klamath Wildlife Resources, Redding, CA, appearing for
Appellant.
Stephanie L. Lynch, Office of the Regional Solicitor, Department of the Interior,
Portland, OR, counsel for Respondent.
Before Board Judges DANIELS (Chairman), VERGILIO, and ZISCHKAU.
Opinion for the Board by Board Judge VERGILIO. Board Judge ZISCHKAU dissents.
VERGILIO, Board Judge.
On March 21, 2014, the Board received from Klamath Wildlife Resources (contractor;
âcontractorâ at times also refers to its owner) a notice of appeal contesting the termination
for default of its task order contract with the Bureau of Land Management, Department of
the Interior (agency or BLM). The contractor was to conduct surveys of northern spotted
owls (NSOs) pursuant to contract requirements including a referenced protocol. For each
survey visit the contractor would make observations at 150 call stations and perform any
necessary follow-up work. At the time of the termination, the contractor had conducted six
CBCA 3764 2
sets of surveys (i.e., six visits to each call station), and had just begun another round of
surveys.
The parties have submitted this case on the written record. The record demonstrates
that the contractor failed to comply with contract requirements when it conducted four-hour,
not the six-hour, follow-up surveys required by the explicit language of the contract. The
contract also required the contractor to provide identifying GPS (geographic or global
positioning system) information for the locations of call stations visited, and to provide, at
the request of the agency, GPS and map information supporting the actual survey conducted.
By not providing the information as required and requested, the contractor failed to satisfy
contract requirements. This negatively impacted the contract because the agency was unable
to verify the accuracy and quality of the work. Based upon each instance of the contractorâs
refusal to act in accordance with contract requirements, the agency was justified in issuing
a termination for default of the task order contract.
The contractor has not demonstrated that its failures to comply with contract
requirements arose from excusable causes. The contractor references its successful
performance of numerous other surveys, its finding of owls during these surveys, and the
designation of its owner as a spotted owl expert. The first two of these items do not impact
this analysis and the contractorâs duty of performance due the agency. Of the third item, the
specific expertise and experience did not assist the contractor in understanding its obligations
under this contract. The contractorâs obligations were express; the agency was not obligated
to renegotiate contract requirements after award. The contractor did not comply with
contract terms; the contractor could not dictate its obligations. Further, while one contracting
officerâs representative refused to talk with the contractor, communicating instead through
email, and the contracting officer did not engage the contractor during performance, these
actions and non-actions did not alter or impact the contractorâs obligations, as the agency
only required the contractor to fulfill the contract requirements. The agency was not required
to lessen the six-hour follow-up survey requirement, to comply with the contractorâs views,
or to rely upon the contractorâs statements that it was satisfactorily performing when the
agency was unable to locate flagging or ensure that the contractor was visiting the correct
spots for the call stations, and the contractor did not provide the information required under
the contract which could have established compliance.
The Board concludes that the termination for default was valid and denies the appeal.
CBCA 3764 3
Findings of Fact
The underlying contract with the Forest Service
1. The contractor has an indefinite delivery, indefinite quantity contract with the
United States Forest Service. Exhibit 3 (all exhibits are in the appeal file). The award date
was April 3, 2012; delivery orders could be placed no later than September 30, 2016. Exhibit
3 at 1-2.