CBCA 2482
Board: CBCA
Agency: Department of Agriculture
Appellant: Choctaw Transportation Company, Inc.
Date: 2016-12-09
Outcome: denied
CBCA 2482 DENIED;
CBCA 2653 GRANTED: December 9, 2016
CBCA 2482, 2653
CHOCTAW TRANSPORTATION COMPANY, INC.,
Appellant,
v.
DEPARTMENT OF AGRICULTURE,
Respondent.
S. Leo Arnold and Matthew W. Willis of Ashley, Ashley & Arnold, Dyersburg, TN,
counsel for Appellant.
Danny L. Woodyard, Office of the General Counsel, Department of Agriculture, Little
Rock, AR; and L. Benjamin Young, Office of the General Counsel, Department of
Agriculture, Washington, DC, counsel for Respondent.
Before Board Judges DANIELS (Chairman), GOODMAN, and DRUMMOND.
GOODMAN, Board Judge.
Appellant, Choctaw Transportation Company, Inc. (Choctaw or appellant), on behalf
of itself and its subcontractor Bertucci Contracting Company, LLC (Bertucci),1 appeals two
decisions issued by a contracting officer of respondent, Department of Agriculture, Natural
Resources Conservation Service (NRCS).
1
Choctaw and Bertucci are referred to in this opinion when witnesses and
documentation specific to each are mentioned.
CBCA 2482, 2653 2
The contract was for the construction of a rock groin and eight breakwaters at
Raccoon Island, in the Gulf of Mexico, off the coast of Louisiana. As more fully detailed
in this decision, appellant submitted its bid for the contract in early August 2005 in the
amount $4,056,032.50. Several weeks later, Hurricane Katrina struck the project site.
Appellant was awarded the contract in early September 2005, and soon thereafter Hurricane
Rita struck the project site and Hurricane Wilma entered the Gulf of Mexico. Respondent
sent a survey team to re-survey the project site, and issued modification 1 to the contract in
December 2005, concurrent with the notice to proceed. Modification 1 made specific
alignment changes to the groin and changes to the breakwaters. In modification 1, the NRCS
contracting officer stated that these changes were âdue to changed water depths as the result
of the hurricane,â and requested that appellant submit a price proposal in response to the
changes ordered in the modification. Appellant and its subcontractor did not submit a price
proposal before beginning performance. Later, during contract performance, appellant
advised that a proposal would be submitted once the work was complete.
Appellant concluded contract performance in September 2007. In February 2010,
appellant submitted a proposal for an equitable adjustment as the result of the changes
ordered in modification 1. The parties were unable to resolve the request for equitable
adjustment. In January 2011, appellant submitted a certified claim on behalf of itself and
Bertucci seeking compensation for delay and disruption resulting from modification 1 in the
amount of $4,144,191.20. On April 15, 2011, respondentâs contracting officer issued a
decision denying the certified claim in its entirety. Appellantâs ensuing appeal of this
decision was docketed as CBCA 2482. On November 21, 2011, respondentâs contracting
officer issued a second decision, asserting a government claim of actual damages against
Choctaw in the amount $15,032.19, and appellantâs appeal of this decision was docketed as
CBCA 2653.
A hearing on the merits in these appeals (the hearing) was held on April 20-24, 2015,
in Washington, D.C. Two fact witnesses testified in support of appellantâs claims:
Mr. Gregory Ford, Choctawâs vice president of operations, and Mr. Anthony Zelenka,
Bertucciâs president.2 Two witnesses designated as experts testified on behalf of appellant:
Mr. Ruben McCoy, a computer-aided design (CAD) consultant, and Mr. William Connole,
a professional engineer, who was tendered as an expert on delay and disruption analysis and
costs. Mr. Ford and Mr. Connole were also called as rebuttal witnesses by appellant.
2
References to âMr. Zelenkaâ in this decision are to Anthony Zelenka. There are
occasional references to Steve Zelenka, Mr. Zelenkaâs brother.
CBCA 2482, 2653 3
Respondent presented the testimony of five fact witnesses: Mr. Ralph Broome, a
procurement analyst for the NRCS, who served as contracting officer for the contract at
issue; Mr. Bradley Sticker, a state construction engineer during the contract period; Mr. Dale
Garber, an engineer for the NCRS and the contracting officerâs technical representative
(COTR) for the contract at issue; Mr.