CBCA 3246
Board: CBCA
Appellant: Regency Construction, Inc.
Date: 2016-08-17
Outcome: dismissed
CBCA 3246 DISMISSED FOR LACK OF JURISDICTION;
CBCA 4356 GRANTED-IN-PART and
DISMISSED-IN-PART FOR LACK OF JURISDICTION: August 17, 2016
CBCA 3246, 4356
REGENCY CONSTRUCTION, INC.,
Appellant,
v.
DEPARTMENT OF AGRICULTURE,
Respondent.
S. Leo Arnold and Matthew W. Willis of Ashley, Ashley & Arnold, Dyersburg, TN,
counsel for Appellant.
Danny L. Woodyard, Office of the General Counsel, Department of Agriculture, Little
Rock, AR, counsel for Respondent.
Before Board Judges SOMERS, VERGILIO, and SULLIVAN.
SULLIVAN, Board Judge.
Appellant, Regency Construction, Inc. (Regency), appeals two decisions of the
contracting officer for respondent, Department of Agriculture, Natural Resources
Conservation Service (NRCS), denying its claim for additional costs of performance on the
task order for canal excavation services in St. Bernard Parish, Louisiana. The appeal of the
first decision, issued by the contracting officer on November 15, 2012, on Regencyâs
uncertified claim, was docketed as CBCA 3246. The appeal of the second decision, issued
CBCA 3246, 4356 2
by the contracting officer on November 25, 2014, after Regency certified its claim, was
docketed as CBCA 4356.
In its claim, Regency sought $292,403, as the costs arising from four different issues
that occurred during performance: (1) delays caused by the continued presence of another
contractor at the site, despite the agencyâs representation that the other contractor would be
finished prior to the start of task order performance; (2) delays in survey work caused by the
NRCS; (3) costs incurred to remove additional material that entered the canal when the sides
of the canal would not maintain the slope that NRCS mandated; and (4) delays Regency
experienced looking for gas pipelines that did not exist. In its appeals, Regency also seeks
the costs paid to a consultant who assisted with contract administration related to these
problems, although these costs were not discussed in its claim to the contracting officer.
The Board convened a hearing in this matter in New Orleans, Louisiana, on
December 9-12, 2014. Two fact witnesses testified in support of Regencyâs claims: Mr.
John Smith, the president and owner of Down To Earth Contracting (DTEC), which was the
subcontractor to Regency for the task order at issue in this appeal; and Mr. Paul Kosbab, the
president and owner of Regency. Mr. Kosbab has been performing excavation and other
storm-related clean-up projects for NRCS since 1989. Transcript at 493-94. Regency also
presented the testimony of two experts: Dr. Berkeley Traughber, geotechnical expert; and
Mr. William Connole, cost and pricing and delay analysis expert.
Three witnesses testified on behalf of the agency: Mr. Brad Sticker, Ms. Cherie
LeFleur, and Mr. Dale Garber. Mr. Sticker is no longer employed by the agency but had held
the title State Conservation Engineer and served as one of the managers of the NRCS
emergency operations center (EOC) in Louisiana during the pendency of the task order.
Transcript at 844-45. That office was responsible for the projects in Louisiana after
Hurricane Katrina. Id. Ms. LeFleur is an environmental engineer with the agency and also
served as a manager of the EOC. Id. at 765. Ms. LeFleur designed the project. Id. at 777.
Mr. Garber is an engineer with NRCS, and served as the contracting officerâs technical
representative (COTR) on the task order for approximately two weeks at the beginning of
January 2008. Id.