CBCA 2953-R
Board: CBCA
Agency: General Services Administration
Appellant: Suffolk Construction Company, Inc.
Date: 2020-04-13
Outcome: granted
MODIFIED ON RECONSIDERATION: April 13, 2020
CBCA 2953-R, 2954-R, 2955-R, 3596-R, 4175-R, 4377-R, 5006-R
SUFFOLK CONSTRUCTION COMPANY, INC.,
Appellant,
v.
GENERAL SERVICES ADMINISTRATION,
Respondent.
James R. Newland, Jr., of Seyfarth Shaw LLP, Washington, DC, counsel for
Appellant.
James F. H. Scott and Justin S. Hawkins, Office of General Counsel, General Services
Administration, Washington, DC, counsel for Respondent.
Before Board Judges SOMERS (Chair), DRUMMOND, and ZISCHKAU.
ZISCHKAU, Board Judge.
Appellant, Suffolk Construction Company, Inc. (Suffolk), and respondent, General
Services Administration (GSA), have moved to amend our decision in Suffolk Construction
Co. v. General Services Administration, CBCA 2953, et al., 20-1 BCA ¶ 37,488 (2019). We
treat their motions as motions for reconsideration. The parties do not contest any of the
entitlement determinations of our decision, but seek adjustments to the quantum award. We
grant reconsideration and amend in part our quantum award.
CBCA 2953-R, 2954-R, 2955-R, 3596-R, 4175-R, 4377-R, 5006-R 2
Background
Familiarity with the underlying decision is presumed. This appeal arose from a
contract GSA awarded to Suffolk for the renovation of the McCormack Building, an historic
building located in Boston, Massachusetts. Suffolk filed appeals seeking $22,766,290, plus
interest, while GSA sought $3,196,437 in claims of its own. We found Suffolk entitled to
a net recovery of $12,583,546, plus interest. Suffolk seeks reconsideration (1) of the Boardâs
award of $1,135,000 for Suffolkâs general conditions claim, and (2) on the failure of the
Board to award commission and insurance/bonding on portions of two subcontractor claims.
GSA seeks reconsideration of the Boardâs jurisdiction to award Suffolkâs contract balance,
and of the award of $314,302 on proposed change order (PCO) 1048 under Suffolkâs PCO
claims.
Discussion
Board Rules 26 and 27 authorize the Board to grant reconsideration or relief for any
reason recognized in Rules 59 and 60 of the Federal Rules of Civil Procedure. See 48 CFR
6101.26(a), 27(a) (2019). These reasons include: justifiable or excusable mistake,
inadvertence, surprise, or excusable neglect; the decision is void, whether for lack of
jurisdiction or otherwise; and any other ground justifying relief from the operation of the
decision or order. See Watermark Environmental, Inc. v. Department of Agriculture, CBCA
2866-R, 15-1 BCA ¶ 36,113. Additionally, Board Rule 29 authorizes the Board to âcorrect
clerical mistakes while a case is pending, or within 60 days thereafter if a decision has not
been appealed.â
Suffolkâs General Conditions Claim
We found Suffolk entitled to $1,135,000 in general conditions costs related to the
period of government delay from May 29, 2009, through March 31, 2010. We calculated the
amount by dividing the period of delay into four phases and multiplying the duration of each
phase by a daily rate that represented Suffolkâs costs during that period. Prior to arriving at
a final number for each period, we accounted for the costs that GSA had already credited to
Suffolk for the government delay, which we noted Suffolk had excluded from its claim. In
this motion, Suffolk requests that we increase the general conditions award from $1,135,000
to $2,265,986. See Appellantâs Motion at 1. Suffolk suggests that âthe Board may have
overlooked the fact that Suffolk had already reduced its claimâ by the amount that GSA had
credited to Suffolk. Id. at 2. The Board did not come to its lower award by double-counting
the amount that GSA had already credited to Suffolk for the delay period. Rather, the Board
found Suffolk entitled to general conditions costs at a lower daily rate particularly for the
later delay periods. We determined that the awarded amount of $1,135,000 reasonably
CBCA 2953-R, 2954-R, 2955-R, 3596-R, 4175-R, 4377-R, 5006-R 3
reflected Suffolkâs additional general conditions costs on its contract work. Accordingly, we
deny Suffolkâs motion to amend the general conditions award.
Commission and Bonding Costs for Suffolkâs Subcontractors
In our decision, we found Suffolk entitled to $4,520,133 for costs associated with the
claims of its subcontractors NB Kenney and City Lights. In calculating quantum for these
subcontractors, the Board mistakenly omitted awarding Suffolkâs 10 % commission and
1.362 % insurance and bond mark-up.