ASBCA 62607
Board: ASBCA
Agency: United States Special Operations Command
Appellant: Vigor Works, LLC
Date: 2023-02-22
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Vigor Works, LLC ) ASBCA No. 62607
)
Under Contract No. H92222-11-D-0080 )
APPEARANCES FOR THE APPELLANT: Mark G. Jackson, Esq.
Stowell B. Holcomb, Esq.
Jackson Holcomb LLP
Seattle, WA
APPEARANCES FOR THE GOVERNMENT: Caryl A. Potter, III, Esq.
Deputy Chief Trial Attorney
Maj Danelle McGinnis, USAF
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE THRASHER
Vigor Works, LLC (Vigor or appellant) appealed under the Contract Disputes
Act (CDA), 41 U.S.C. §§ 7101-7109, from a contracting officerâs final decision
(COFD) denying appellantâs certified claim in the amount of $5,213,618. Vigor seeks
excess costs incurred from what it describes as the government constructively changing
the contract by accelerating the production pace and sequence through the issuance of
delivery orders. The parties have elected a written disposition under Board Rule 11.
We deny the appeal.
FINDINGS OF FACT
1. On September 28, 2011, the United States Special Operations Command
(SOCOM or government) awarded Contract No. H92222-11-D-0080 (the contract) to
Vigor Works, LLC 1 (R4, tab 9). The contract was for the design, development, and
fabrication of Combatant Craft, Medium Mark 1 (CCM Mk 1) systems (compl. ¶ 7;
R4, tab 9a at 4).
2. The contract was an indefinite-delivery, indefinite-quantity (IDIQ) contract
with firm-fixed-price and cost reimbursable contract line items (CLINs) for a total
period of performance of ten years, including option periods (R4, tab 9 at 3). Part I of
the contract contained âTHE SCHEDULEâ (R4, tab 9 at 2).
1
SOCOM awarded the contract to Oregon Iron Works, Inc. (OIW), but OIW later
became Vigor Works, LLC (R4, tab 36 at 3; app. supp. R4, tab 25 at 3).
3. The Schedule, Section B, Supplies or Services and Prices, divided the
CLINs into four successive periods:
⢠Base Period (CLINs 0001-0008)
⢠If applicable, Test Article Refurbishment (CLINs 0009-0018)
⢠If applicable, Low Rate Initial Production (CLINs 0019-0044)
⢠If applicable, seven Production/Sustainment Ordering Periods (CLINs 1001-
7027)
(R4, tab 9 at 3) Each CLIN was to be âset forth under individual delivery orderâ and
performed âin accordance with Sections C 2 and Jâ of the contract (see R4, tab 9 at 4-
126).
4. The Schedule, Section F, Deliveries or Performance, established delivery
information for each CLIN, including delivery dates for CLINs 0001 to 7027 (R4,
tab 9 at 1, 133-46).
5. Part III of the contract contained âLIST OF DOCUMENTS, EXHIBITS
AND OTHER ATTACHMENTSâ (R4, tab 9 at 1). Section J listed the documents,
exhibits, and other attachments. The first item listed is Exhibit A, Contract Data
Requirements Listings A, E, L, dated August 11, 2011. (R4, tab 9 at 182; see also R4,
tab 9k) The contract required the contractor to provide several Contract Data
Requirement Lists (CDRLs), including A006 Integrated Program Master Schedule
(IPMS) (R4, tab 9 at 6).
6. The Data Description for A006 IPMS provides:
1) The Contractor shall prepare, maintain, and update a
CCM Mk 1 Integrated Program Master Schedule
(IPMS) that reflects the Contractorâs program and
schedule planning. The Contractor shall ensure the
IPMS reflects the baseline schedule and all changes
thereto and maintain the IPMS throughout the life of
the contract.
2
There is no âXâ under Part I, Section C, Description/Specs/Work Statement. The
contract included the Statement of Work as Attachment 01 under Section J (see
R4, tab 9 at 1, 182).
2
2) The IPMS shall contain the networked, detailed tasks
necessary to ensure successful program execution. The
IPMS is vertically traceable to the Contract Work
Breakdown Structure (CWBS), and the Statement of
Work (SOW).