CBCA 5527
Board: CBCA
Agency: Department of Veterans Affairs
Appellant: Hawk Contracting Group, LLC
Date: 2016-12-02
Outcome: denied
DENIED: December 2, 2016
CBCA 5527
HAWK CONTRACTING GROUP, LLC,
Petitioner,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
Thomas R. Krider and Alix K. Town of Oles Morrison Rinker & Baker LLP, Seattle,
WA, counsel for Petitioner.
Jennifer L. Hedge, Office of General Counsel, Department of Veterans Affairs,
Pittsburgh, PA, counsel for Respondent.
Before Board Judges VERGILIO, KULLBERG, and LESTER.
LESTER, Board Judge.
Pursuant to section 7103(f)(4) of the Contract Disputes Act (CDA), 41 U.S.C.
§§ 7101-7109 (2012), and Board Rules 1(b)(7) and 2(a)(2) (48 CFR 6101.1(b)(7), .2(a)(2)
(2015)), petitioner, Hawk Contracting Group, LLC (Hawk), requests that the Board direct
the Department of Veterans Affairs (VA) contracting officer to issue a decision earlier than
the date that the contracting officer has identified for its expected issuance. For the reasons
set forth below, we deny Hawkâs request.
CBCA 5527 2
Background
On September 17, 2013, the VA awarded contract no. VA69D-13-C-0289 (the
contract) to Hawk to remodel and expand the material management area at the Jesse Brown
Veterans Affairs Medical Center in Chicago, Illinois. The VA terminated the contract for
the convenience of the Government on June 11, 2015, and requested that Hawk submit a
termination settlement proposal. Hawk submitted that proposal on December 31, 2015,
along with a cover letter expressing a desire for a prompt resolution of the negotiation and
settlement process.
On January 29, 2016, in response to a status update request from Hawk, the VA
indicated that, pursuant to the requirements of the Federal Acquisition Regulation (FAR),
it would need to audit Hawkâs proposal because Hawk was seeking recovery of more than
$100,000. Over the course of the next few months, Hawk sought further updates from the
VA and was eventually informed that the VA Office of the Inspector General (OIG) had
declined the contracting officerâs request for an audit of Hawkâs proposal, requiring the VA
to search for a private contractor if it wished to have an audit conducted. Subsequently, the
VA informed Hawk that an audit had been deemed not to be feasible.
After further negotiations did not result in a settlement, Hawk on August 4, 2016,
converted its termination settlement proposal into a certified claim and requested that the VA
contracting officer issue a decision within sixty days, in accordance with the contractâs
Disputes clause. On October 3, 2016, the VA contracting officer notified Hawk that he
anticipated a decision on or before January 20, 2017.
On October 24, 2016, Hawk filed its current petition with the Board, asking that we
direct the contracting officer to issue his decision no later than November 30, 2016. Hawk
further requested that, to the extent that the VA contracting officer does not comply with that
Board order and issue a decision by November 30, 2016, the Board permit Hawk to appeal
the contracting officerâs âdeemed denialâ immediately thereafter. Finally, Hawk has
requested that, to the extent that we do not shorten the contracting officerâs existing deadline
of January 20, 2017, we preclude any further extensions beyond that date.
Discussion
Pursuant to the CDA, within sixty days of receiving a contractorâs written certified
claim of more than $100,000, the contracting officer must either issue a decision on the
claim or notify the contractor âof the time within which a decision will be issued.â 41
U.S.C. § 7103(f)(2). If the contracting officer fails to issue a decision on the claim âwithin
the required time period,â that failure may be âdeemed to be a decision by the contracting
CBCA 5527 3
officer denying the claim and authorizes an appeal or action on the claimâ before,
respectively, a board of contract appeals or the Court of Federal Claims. Id. § 7103(f)(5).
Here, before the sixty-day period for issuing a decision on Hawkâs claim had expired,
the contracting officer indicated that he anticipated issuing a decision on or before January
20, 2017. We treat this as a commitment to issuing a decision no later than that date. Until
there is a decision on Hawkâs claim, or the date for issuance passes, Hawk cannot maintain
an appeal with the Board or a suit at the Court of Federal Claims on its claim. See Paragon
Energy Corp. v. United States, 645 F.2d 966, 971 (Ct. Cl.