ASBCA 62070
Board: ASBCA
Agency: Department of the Army
Appellant: Advanced Global Resources, LLC
Date: 2019-09-10
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of -- )
)
Advanced Global Resources, LLC ) ASBCA No. 62070
)
Under Contract No. W911RQ-18-D-0001 )
APPEARANCE FOR THE APPELLANT: David Yang, Esq.
Oles Morrison Rinker Baker, LLP
Seattle, WA
APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq.
Army Chief Trial Attorney
MAJ Wayne T. Branom III, JA
CPT Jeremy D. Burkhart, JA
Trial Attorneys
OPINION BY ADMINISTRATIVE JUDGE D' ALESSANDRIS
In December 201 7, respondent, the Department of the Army (government or
Army) awarded a contract for information technology support services to appellant,
Advanced Global Resources, LLC (AGR). A few days later, the award was protested
to the Government Accountability Office (GAO), and the Army issued a stop work
order (SWO) due to the protest. After GAO denied the protest, the Army lifted the
SWO. AGR now seeks reimbursement of direct costs and extended home office
overhead costs purportedly incurred during the SWO period. Appellant elected to
proceed under the Board's Small Claims (Expedited) procedures, Board Rule 12.2.
The Contract Disputes Act, 41 U.S.C. §§ 7106 (b)(4)-(5), as implemented by
Board Rule 12.2, provides that this decision shall have no precedential value, and
in the absence of fraud shall be final and conclusive and may not be appealed or
set aside. For the reasons stated below, AGR's appeal is denied.
FINDINGS OF FACT
On December 14, 2017, the Army awarded to AGR Contract No. W911RQ-18-D-0001
for information technology support services at the Red River Army Depot (R4, tab 1).
On December 19, 2017, the Army issued Task Order 0001 and Task Order
Modification 000101 under the Contract (R4, tab 2; app. supp. R4, tab 23). Neither the
Base Contract nor the Task Order contained terms regarding protests before GAO or
stays of performance under FAR 52.233-3 "PROTEST AFTER AWARD" (R4, tabs 1-2).
That FAR clause provides that "[t]he Contracting Officer shall make an equitable 1·
adjustment in the delivery schedule or contract price, or both, and the contract shall be ,
,
l
modified, in writing, accordingly, if- (1) The stop-work order results in an increase in
the time required for, or in the Contractor's cost properly allocable to, the performance of
any part of this contract." FAR 52.233-3(b). In addition the contract contains 52.212-5
"CONTRACT TERMS AND CONDITIONS REQUIRED To IMPLEMENT STATUTES OR
EXECUTIVE ORDERS-COMMERCIAL ITEMS (DEVIATION 2013-00019) (JAN 2017)" (R4,
tab 1 at 106-07). Unlike the standard FAR provision 52.212-5, the deviation included in
the contract does not incorporate 52.233-3. However, FAR 33.106 "SOLICITATION
PROVISION AND CONTRACT CLAUSE" provides that "(b) The contracting officer shall
insert the clause at 52.233-3, Protest After Award, in all solicitations and contracts."
The day after Contract award, on December 15, 2017, AGR entered into an
employment contract with Mr. Michael McKissick (R4, tab 15b at attach. 1). On
December 22, 2017, the contracting officer notified AGR to stop work under the
Contract because a GAO protest of the award had been filed by the incumbent contractor
(R4, tab 3; A-B Computer Solutions, Inc., B-415819, 2018 CPD 1128, (Comp. Gen.
Mar. 22, 2018)). The task order provided for a phase in period where AGR would
cross-train with the incumbent contractor (R4, tab 1 at 58). AGR performed only
unbillable transition work prior to receipt of the SWO (tr. 1/45). The text of the SWO
reads in relevant part:
[I]n accordance with FAR 52.233-3, Protest After Award,
AGR, LLC is hereby notified to stop performance under
subject contract. AGR, LLC shall not purchase materials
or services related to this Contract until notified by the
Contracting Office. AGR, LLC shall take all reasonable
steps to minimize incurring costs associated with this
stop-work order.
(R4, tab 3) AGR acknowledged receipt of the Stop-Work Order (SWO) the same day,
December 22, 2017 (R4, tab 4).
The SWO did not expressly require AGR to be "on stand-by." However, it did
explain that the SWO was being issued in response to a post-award protest.