CBCA 5540
Board: CBCA
Agency: Department of Veterans Affairs
Appellant: Mare Solutions, Inc.
Date: 2018-05-16
Outcome: granted
CBCA 5540 GRANTED;
CBCA 5541 DISMISSED;
CBCA 6037 DENIED: May 16, 2018
CBCA 5540, 5541, 6037
MARE SOLUTIONS, INC.,
Appellant,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
James R. Mall of Meyer, Unkovic & Scott LLP, Pittsburgh, PA, counsel for
Appellant.
Neil S. Deol, Office of General Counsel, Department of Veterans Affairs, Decatur,
GA, counsel for Respondent.
Before Board Judges ZISCHKAU, RUSSELL, and OâROURKE.
OâROURKE, Board Judge.
The Department of Veterans Affairs (VA) issued solicitation number VA244-14-B-
0079 for the construction of a two-story parking garage at the VA Medical Center (VAMC)
in Erie, Pennsylvania. Attached to the solicitation were 1832 pages of specifications and 172
pages of drawings developed by the VAâs design services contractor, Westlake Reed
Leskosky (WRL or AE).1 A public bid opening was held on March 27, 2014. On May 6,
1
WRL is the architect-engineering (AE) firm that developed the design for the
garage. Exhibit 121 (all exhibits are found in the appeal file unless otherwise noted).
CBCA 5540, 5541, 6037 2
2014, the contract was awarded to Mare Solutions, Inc. (Mare), a service-disabled, veteran-
owned small business in Pittsburgh.
When the project was nearly complete, two disputes arose between the parties, one
involving buckled metal conduit on the first floor ceiling of the garage and the other
regarding which party was responsible for purchasing âhead-endâ equipment for the video
surveillance system. The contracting officer (CO) issued final decisions on both issues,
which Mare disagreed with and timely appealed to the Board. Mare sought declaratory relief
in both appeals, requesting an interpretation of the contractâs terms that absolved it of
liability for the buckled conduit and for the purchase of head-end equipment. Those appeals,
dated November 7, 2016, were docketed as CBCA 5540 and CBCA 5541.
During a hearing in May 2017, Mare testified that it had purchased and installed the
head-end equipment and now sought reimbursement for the equipment costs. The buckled
conduit, on the other hand, remained a live performance dispute. The Board raised concerns
about its jurisdiction to decide the video equipment dispute since a monetary claim was never
presented to the contracting officer. To resolve those concerns, Mare filed a claim for the
costs of the equipment on February 9, 2018. The contracting officer denied the claim, and
Mare filed a third appeal at the Board on February 16, 2018. That appeal was docketed as
CBCA 6037. All three appeals were consolidated and are decided here.
Findings of Fact
I. The Buckled Conduit â CBCA 5540
The dispute over the buckled conduit primarily involved whether expansion
couplings2 should have been installed on the conduit. Although the contract included
specifications for expansion couplings, the parties disagreed on whether the conditions
requiring their installation were present in the parking garage.
A. Specifications, Drawings, and Relevant Contract Terms
Specification 26 05 11, part one, paragraph 1.1.B (Requirements for Electrical
Installations) required the contractor to â[f]urnish and install electrical wiring, systems,
equipment and accessories in accordance with the specifications and drawings.â Paragraph
2
An expansion coupling is âan electrical fitting for a conduit run that would allow
for expansion . . . on the conduit run.â Transcript at 79.
CBCA 5540, 5541, 6037 3
1.2.A (Minimum Requirements) established the National Electrical Code (NEC) as a
minimum standard for installation of the conduit.3 Exhibit 1 at 1031.
Specification 26 05 33 (Raceway and Boxes for Electrical Systems) called for the
âfurnishing, installation, and connection of conduit, fittings, and boxes, to form complete,
coordinated, grounded raceway systemsâ throughout the garage. Conduit was defined as
âany or all of the raceway types specified.â Exhibit 1 at 1063. Part two of the specification
identified the following products for use relevant to conduit and expansion couplings:
C.6. Surface metal raceway fittings: As recommended by the raceway
manufacturer. Include couplings, offsets, elbows, expansion joints, adapters,
hold-down straps, end caps, conduit entry fittings, accessories, and other
fittings as required for [a] complete system.
C.7.