ASBCA 63148
Board: ASBCA
Agency: U.S. Army Engineer District, Tulsa
Appellant: Korte Construction Company
Date: 2023-10-26
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Korte Construction Company ) ASBCA No. 63148
)
Under Contract No. W912BV-19-C-0017 )
APPEARANCE FOR THE APPELLANT: Michael E. Wilson, Esq.
Greenfelder, Hemker & Gale, P.C.
St. Louis, MO
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Lauren M. Williams, Esq.
Thomas R. Alford, Esq.
Engineer Trial Attorneys
U.S. Army Engineer District, Tulsa
OPINION BY ADMINISTRATIVE JUDGE STINSON
ON THE PARTIES’ MOTIONS FOR SUMMARY JUDGMENT
Appellant Korte Construction Company (Korte) appeals a contracting officer’s
October 22, 2021, final decision denying Korte’s August 24, 2021, claim requesting
the government rescind its unilateral contract modification assessing a credit of
$493,639.43, in direct and indirect costs for a deductive change to contract work. We
have jurisdiction pursuant to the Contract Disputes Act of 1978 (CDA), 41 U.S.C.
§§ 7101-7109. The parties submitted opposing motions for summary judgment,
responsive and reply briefs, as well as exhibits to be considered in deciding this
appeal. 1 For the reasons stated below, appellant’s motion for summary judgment is
denied and the government’s motion for summary judgment is granted.
1
“App. mot.” refers to appellant’s March 20, 2023, motion for summary judgment;
“gov’t mot.” refers to the government’s March 20, 2023, motion for summary
judgment; “app. resp.” refers to appellant’s May 10, 2023, response to the
government’s motion for summary judgment; “gov’t resp.” refers to the
government’s May 10, 2023, response to appellant’s motion for summary
judgment; “app. reply” refers to appellant’s June 9, 2023, reply brief; and
“gov’t reply” refers to its June 9, 2023, reply in support of its motion for
summary judgment.
SYNOPSIS
This appeal presents the issue of whether the government is entitled to a credit
under a deductive change request where the contractor alleges it did not include in its
cost proposal amounts required to perform work that is the subject of the deductive
change request. Korte offers evidence that its mechanical subcontractor, who
submitted a bid for the work that was incorporated into the contractor’s cost proposal,
determined that the work was not required under the contract, and, accordingly, did not
price that work.
Korte now seeks to use as a shield the fact that, through incorporation of its
subcontractor’s bid into its cost proposal, Korte’s contract price did not include the
cost to perform work covered by the deductive change order and, as such, the
government is not entitled to a credit for the work not performed. While it is true that,
for certain purposes, a subcontractor’s interpretation will be imputed to a contractor if
it proves that the subcontractor relied upon that interpretation in submitting its bid, the
defect in Korte’s armor is that the contractor is not protected if the interpretation by
the subcontractor is indefensible, and here, the evidence Korte offers in its motion for
summary judgment establishes that its subcontractor recognized pre-award an
ambiguity in the contract regarding whether the work was required to be performed
but did not seek clarification regarding that work. Korte suggests that reference to the
work in the solicitation was simply a scrivener’s error, one it admittedly had
knowledge of during the solicitation process. However, Korte’s motion for summary
judgment admits knowledge of an ambiguity in the solicitation, one which appellant
was required to raise with the government pre-award but failed to do so.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS
The parties submitted a Joint Stipulation of Material Facts (JSMF) in support of
their motions for summary judgment. Our statement of facts relies upon, and adopts,
certain of the parties’ JSMF, as set forth below.
RFP Phase 1
1. On October 11, 2018, the government issued the Phase 1 Request for
Proposals (RFP) for Solicitation No. W912BV-18-R-0047 (JSMF ¶ 1; R4, tab 3).