CBCA 6477-R
Board: CBCA
Agency: Department of Energy
Appellant: Mission Support Alliance, LLC
Date: 2022-10-20
Outcome: denied
RECONSIDERATION DENIED: October 20, 2022
CBCA 6477-R
MISSION SUPPORT ALLIANCE, LLC,
Appellant,
v.
DEPARTMENT OF ENERGY,
Respondent.
Marisa M. Bavand and Allison L. Murphy of Groff Murphy PLLC, Seattle, WA,
counsel for Appellant.
Paul R. Davis and Andrew J. Unsicker, Office of Chief Counsel, Department of
Energy, Richland, WA, counsel for Respondent.
Before Board Judges GOODMAN, DRUMMOND, and CHADWICK.
CHADWICK, Board Judge.
Mission Support Alliance, LLC (MSA) timely sought reconsideration under Board
Rule 26 (48 CFR 6101.26 (2021)) of our August 2022 decision denying MSAâs appeal of a
government claim under a cost-type contract. We found that MSA did not meet its burden
to prove the reasonableness of $333,895 it paid to three subcontractors. MSA argues that,
in fact, it âpresented hard evidence via exhibits, testimony and briefing that the costs were
allowable and reasonable.â We deny reconsideration but clarify our decision in part.
Grounds to reconsider a Board decision may include, among other things, âclear
error,â which is what we understand MSA to assert here. See, e.g., Walker Development &
Trading Group Inc. v. Department of Veterans Affairs, CBCA 5907-R, 19-1 BCA ¶ 37,465,
CBCA 6477-R 2
at 182,010. MSA argues that we overlooked record evidence that âthe disputed costs are
reasonable because [MSA followed] its Purchasing System procedures . . . , which had been
reviewed and approved by DOE [the respondent, Department of Energy,] and its auditor . . . ,
for reviewing and approving subcontractor work and costs.â
We disagree that we improperly neglected to address such evidence. As we wrote,
âWe know of no authority . . . suggesting that evidence of mere âreviewâ and âapprovalâ by
contractor personnel suffices to show that subcontractor charges are reasonable.â Mission
Support Alliance, LLC v. Department of Energy, CBCA 6477, slip op. at 6 (Aug. 17, 2022)
(citing 48 CFR 31.201-3(a) (2018) (âNo presumption of reasonableness shall be attached to
the incurrence of costs.â)). We did not consider MSAâs arguments that it followed its own
procedures to be material. Rather, â[a] cost is reasonable if, in its nature and amount, it does
not exceed that which would be incurred by a prudent person in the conduct of competitive
business.â 48 CFR 31.201-3(a) (emphasis added). Proof of reasonableness should entail
some âindependent evidence of the reasonablenessâ of the dollars spentânot merely
evidence of the contractorâs own behavior. See Kellogg Brown & Root Services, Inc.
v. United States, 728 F.3d 1348, 1363 (Fed. Cir. 2013); see also Kellogg, Brown & Root
Services, Inc. v. Secretary of the Army, 973 F.3d 1366, 1373 (Fed. Cir. 2020) (noting, inter
alia, that a sophisticated defense contractor âonly offered conclusory testimony, unsupported
by any data or evidence in the record, that [a] daily rate of $300 was . . . reasonableâ).
We find, therefore, that by reemphasizing the evidence relating to its internal
purchasing procedures, MSA raises only â[a]rguments and evidence previously presentedâ
and addressed, which âare not grounds for reconsideration.â Rule 26(a). We also conclude,
however, that some language in our decision warrants amplification. We repeatedly stated
that MSA cited ânoâ evidence of cost reasonableness. Mission Support Alliance, slip op. at
5â7. The context of those statements was that MSA denied bearing any burden of proof.
See id. at 4 n.4. MSA argued at pages 41â42 of its post-hearing brief, âTo MSAâs
knowledge, DOE is not challenging the reasonableness or allocability of the costs. . . . [I]t
is up to the government to show that costs incurred by a contractor are unallowable . . . . The
Government bears the burden of proof when the government is not disputing the
reasonableness or allocability of costs incurred under a particular contract.â (Emphasis
added.) We explained that MSA was mistaken and that it needed to prove reasonableness
to defeat DOEâs claim. Id. (âIt is true that an unreasonable cost is also unallowable . . . , but
this case is at bottom about reasonableness, and MSA bears the burden of proof per 48 CFR
31.201-3(a).â).
In this context, we understood MSA to be arguing only that DOE failed to satisfy a
burden of proof that, we held, DOE did not actually bear. MSA repeatedly argued at pages
75â92 of its post-hearing brief that its costs were âsupported and allowableâ because they
were internally âreviewed and approvedâ and that DOE could not prove otherwise.