ASBCA 63112
Board: ASBCA
Agency: Navy
Appellant: Doubleshot, Inc.
Date: 2022-07-19
Outcome: granted
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Doubleshot, Inc. ) ASBCA No. 61691
)
Under Contract No. N6835-06-C-0416 et al. )
APPEARANCE FOR THE APPELLANT: Mr. Alan Shulman
CEO
APPEARANCES FOR THE GOVERNMENT: Arthur M. Taylor, Esq.
DCMA Chief Trial Attorney
Srikanti Schaffner, Esq.
Trial Attorney
Defense Contract Management Agency
Carson, CA
OPINION BY ADMINISTRATIVE JUDGE OâCONNELL ON
APPELLANTâS MOTION FOR PARTIAL SUMMARY JUDGMENT
Appellant, Doubleshot, Inc. (Doubleshot), has filed a motion for partial
summary judgment contending that it is entitled to judgment as a matter of law on the
governmentâs claim to the extent that it is based on (1) missing or unsigned time cards
and (2) disallowed independent research and development and bid and proposal costs.
The Board grants Doubleshotâs motion with respect to time cards but denies it with
respect to independent research and development and bid and proposal costs.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
The following facts are undisputed or uncontroverted, except as noted below
with respect to the date Doubleshot produced its general ledger. The government has
not disputed any of Doubleshotâs proposed material facts not in dispute (AMF).
This is Doubleshotâs second motion for summary judgment. Doubleshot, Inc.,
ASBCA No. 61691, 20-1 BCA ¶ 37,677 (Doubleshot I) recon. denied, 20-1 BCA
¶ 37,741. We restate the facts only to the extent necessary in this opinion.
1. As related in Doubleshot I, the parties entered into the following four
contracts:
Naval Air Warfare Center Contract No. N68335-06-C-0416 (the 416 contract)
dated September 14, 2006 (R4, tab 1);
U.S. Army Tank-automotive and Armaments Command (TACOM) Contract
No. W56HZV-07-C-0295 (the 295 contract) dated March 22, 2007 (R4, tab 2);
Office of Naval Research Contract No. N00014-07-C-0386 (the 386 contract)
dated June 13, 2007 (R4, tab 5); and
Office of Naval Research Contract No. N00014-08-C-0497 (the 497 contract)
dated September 11, 2008 (R4, tab 11).
Doubleshot I, 20-1 BCA ¶ 37,677 at 182,902.
2. The contracts were all at least in part cost-plus-fixed-fee and incorporated
Federal Acquisition Regulation (FAR) clause 52.216-7, ALLOWABLE COST AND
PAYMENT (DEC 2002) and FAR 52.215-2, AUDIT AND RECORDS â NEGOTIATION
(JUN 1999) (AMF ¶ 2; R4, tab 1 at 18; tab 2 at 16; tab 5 at 12; tab 11 at 12-13 1). The 416
contract incorporated DFARS 252.215-7002 COST ESTIMATING SYSTEM
REQUIREMENTS (OCT 1998) 2 (R4, tab 1 at 19). (The 295 contract incorporated DFARS
252.242-7004, MATERIAL MANAGEMENT AND ACCOUNTING SYSTEM
(NOV 2005) (R4, tab 2 at 17).
Time Cards â Missing and Unsigned
3. The larger of the two issues in the governmentâs claim relates to
Doubleshotâs time cards. The following events are relevant to the contentions raised
in Doubleshotâs motion.
4. On January 28, 2010, the Defense Contract Audit Agency (DCAA) visited
Doubleshotâs office and conducted an examination of Doubleshotâs accounting
system. As described in Doubleshot I, DCAA found the accounting system to be
ânon-existent.â Doubleshot I, 20-1 BCA ¶ 37,677 at 182,903. DCAA detailed the
issues it had identified in what it called a âFlash Reportâ that it issued more than
15 months later, on April 29, 2011. Id. (citing R4, tab 25 at 3).
1
R4 citations are to the .pdf page of the electronic file.
2
Both the 386 and 497 contracts incorporate this clause, but then state that the clause
is only applicable if the contract was awarded based on certified cost or pricing
data, which is not the case for either contract (R4, tab 5 at 16, tab 11 at 17)
2
5. By the time these events had occurred, the relevant Doubleshot fiscal years
(FYs) had ended. Doubleshot FY 2009 ended on February 28, 2009. Doubleshot
FY 2010 ended on February 28, 2010. Doubleshot failed to submit final indirect cost
rate proposals (ICRPs) within six months of each of those dates as required by the
Allowable Cost and Payment clause, FAR 52.216-7(d)(2)(i). Id. at 182,904;
(AMF ¶ 5) Ultimately, Doubleshot submitted revised ICRPs for both FY 2009 and
FY 2010 on September 25, 2013 (R4, tab 28 at 25, tab 29 at 31).
6. More than two years later, on November 30, 2015, DCAA notified
Doubleshot that it would conduct an audit of its FY 2009 and 2010 proposals
(AMF ¶ 6).