ASBCA 61989
Board: ASBCA
Agency: Army Corps of Engineers
Appellant: Maverick Constructors, LLC
Date: 2025-02-19
Outcome: denied
DOCUMENT FOR PUBLIC RELEASE.
The decision issued on the date below is subject to an ASBCA Protective Order.
This version has been approved for public release.
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Maverick Constructors, LLC ) ASBCA No. 61989
)
Under Contract No. W912EP-13-C-0033 )
APPEARANCES FOR THE APPELLANT: James E. Krause, Esq.
James E. Krause, P.A.
Jacksonville, FL
Joseph W. Lawrence, II, Esq.
Vezina, Lawrence & Piscitelli, P.A.
Fort Lauderdale, FL
Devin Maxwell, Esq.
Law Offices of Devin Maxwell
Okeechobee, FL
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Kristin Bigham, Esq.
Sharon Shim, Esq.
Catherine Awasthi, Esq.
James M Zaleski, Esq.
Engineer Trial Attorneys
U.S. Army Engineer District, Jacksonville
OPINION BY ADMINISTRATIVE JUDGE WILSON
This appeal arises from a construction project in Hendry County, Florida.
Appellant, Maverick Constructors, Inc. (Maverick or appellant), challenges the
contracting officerâs denial of all nine of its certified claims. Within these claims,
appellant argues that it is entitled to monetary compensation and time extensions for
delays associated with certain issues that it allegedly encountered during construction,
including a differing site condition, a constructive change, a design defect, and the
governmentâs alleged decision to delay the contract closing date.
DOCUMENT FOR PUBLIC RELEASE.
The decision issued on the date below is subject to an ASBCA Protective Order.
This version has been approved for public release.
The Board conducted six hearing dates between January and August 2022,
at which Vice Chairman Shackleford presided 1. For the reasons stated below, the
Board denies the appeal in its entirety.
FINDINGS OF FACT
1. On August 9, 2013, the United States Army Corps of Engineers (USACE or
Corps) issued Solicitation No. W912EPâ13âBâ0006 for the construction of âwater
resource area levees, canals, pumping stations, control structures, siphon, access
roadways, and associated appurtenant workâ in connection with the Big Cypress
Seminole Indian Reservation Western Water Conservation Restoration Project, Basin
2 and Siphon 2 (âthe Projectâ) in Hendry County, Florida (R4, tab 5 at 1044, 1289).
2. The Project aimed to ârehydrate wetlands, improve water quality and water
storage capacity on the Seminole Tribeâs Big Cypress Basin Reservation, the Big
Cypress National Preserve, and the Everglades Protection Areaâ (compl. ¶ 29).
3. The Solicitation stated that the scope of work to be performed in Basin 2
would include:
a. Clearing and grubbing of rightâofâways for levee and
canal construction.
b. Excavation of canals and placement of compacted
embankment fill for levees, berms, and access
roadways for Water Resource Areas 2E and 2W.
c. Excavation of new drainage canals and cleaning of
existing drainage canals.
d. Installation of Siphon 2 including inlet and outlet
control structures, 60" diameter piping, and excavation
of spreader canals.
e. Construction of four pumping stations.
f. Installation of water control structures fabricated from
corrugated aluminum culverts. Structures may include
light duty sluice gates, concrete headwalls, and access
catwalks.
g.