CBCA 7147
Board: CBCA
Agency: DEPARTMENT OF STATE
Appellant: Williams Building Company, Inc.
Date: 2025-11-21
Outcome: granted
RESPONDENT’S MOTION FOR PARTIAL SUMMARY JUDGMENT
GRANTED IN PART: November 21, 2025
CBCA 7147, 8110
WILLIAMS BUILDING COMPANY, INC.,
Appellant,
v.
DEPARTMENT OF STATE,
Respondent.
Kevin M. Cox of Camardo Law Firm, P.C., Auburn, NY, counsel for Appellant.
Randal W. Wax, Office of the Legal Adviser, Buildings and Acquisitions, Department
of State, Washington, DC, counsel for Respondent.
Before Board Judges LESTER, VERGILIO, and O’ROURKE.
LESTER, Board Judge.
This appeal involves a dispute over the amount of money that appellant, Williams
Building Company, Inc. (WBC), is owed under its termination settlement proposal (TSP),
which it submitted after the Department of State’s Office of Overseas Building Operations
(OBO) terminated its construction contract for convenience.
Pending before us is OBO’s motion for partial summary judgment on two issues
relating to WBC’s entitlement. First, OBO asks us to find that, except for settlement
expenses, WBC cannot recover more than the contract price (less the portion of the contract
price already paid) as part of its convenience termination settlement. Second, it wants the
CBCA 7147, 8110 2
Board to find that WBC would have incurred a monetary loss on this contract had it been
required to complete the project rather than terminated for convenience. OBO is not asking
us at this point in time to identify what the amount or scope of the loss would have been. It
asks us only to find that WBC would have suffered a loss, which, if true, would preclude
WBC from recovering any profit on the contract as part of its termination settlement.
It is well-settled that a terminated contractor’s recovery is limited to the contract price,
less the monies already paid to the contract during performance, plus settlement expenses.
In addition, it is well-settled that, if a terminated contractor would have been in a loss
position had it been required to complete its contract work, the contractor is not entitled to
recover profit as part of its termination settlement, as provided in the relevant Federal
Acquisition Regulation (FAR) clause. It is difficult to apply those basic propositions to this
case at this time, though, based upon the state of the record here. Because we cannot resolve
all of WBC’s claimed entitlements to price increases through the existing motion, we cannot
define the final contract price. Further, to determine whether WBC would have incurred a
loss on this contract if completed, we must know (1) the total contract price, as adjusted by
any equitable adjustments to which the contractor is entitled; (2) the total costs that the
terminated contractor incurred in performing the project; and (3) the total additional costs
that the contractor would have incurred had it been required to complete the contract. The
parties disagree on what the final contract price should be, how much WBC actually spent
on the contract, and the amount that it would have cost WBC to complete the project.
Although, as discussed below, we can dispose on summary judgment of some of the claimed
contract price increases that WBC is pursuing, we cannot identify the precise contract price
that will be input into the loss formula until all of WBC’s pending arguments regarding
actionable changes are resolved. Further, we have no basis for resolving on summary
judgment the parties’ disagreement as to how much WBC incurred in working the project or
how much it would have cost WBC to complete contract performance.
OBO tells us that we need not precisely define contract price or cost to complete
because, even if we accept WBC’s numbers, WBC would still have been in a loss position
based upon the costs that it alleges it incurred during performance. Applying various
combinations of numbers representing a possible final contract price, costs incurred, and cost
to complete, we cannot see how OBO’s assertion is correct. Although some combinations
would result in a loss contract, others would not. There is simply too much uncertainty in
the numbers for the Board to make determinations on summary judgment.