CBCA 5395
Board: CBCA
Agency: Department of Energy
Appellant: CB&I AREVA MOX Services, LLC
Date: 2016-12-15
Outcome: denied
DENIED: March 23, 2017
CBCA 5395
CB&I AREVA MOX SERVICES, LLC,
Appellant,
v.
DEPARTMENT OF ENERGY,
Respondent.
Noah M. Hicks II and James A. Ouellette Jr. of CB&I AREVA MOX Services, LLC,
Aiken, SC, counsel for Appellant.
Matthew Butsick, Office of the General Counsel, National Nuclear Security
Administration, Department of Energy, Washington, DC; and Mary-Ellen Noone, Office of
the General Counsel, National Nuclear Security Administration, Department of Energy,
Aiken, SC, counsel for Respondent.
Before Board Judges DANIELS (Chairman), KULLBERG, and SULLIVAN.
DANIELS, Board Judge.
CB&I AREVA MOX Services, LLC (MOX Services) claims that it is entitled to a fee
of .25% more than the Department of Energyâs (DOEâs) National Nuclear Security
Administration (NNSA) paid, during a specified period of time, for work performed under
a contract between the two parties. The parties have filed cross-motions for summary relief
as to the dispute. We grant DOEâs motion, deny MOX Servicesâs motion, and thereby deny
the appeal.
CBCA 5395 2
Background
On March 22, 1999, DOE awarded to a predecessor in interest to MOX Services a
contract for mixed oxide (MOX) fuel fabrication and reactor irradiation services. The
contract contemplated that the services would include the design and planning of a domestic
MOX fuel fabrication facility [MFFF] and could also include, if options were exercised,
acquisition of materials, construction, installation, and cold start-up (option 1); hot start-up
and MFFF operations (option 2); and deactivation of the MFFF (option 3).1 DOE had the
unilateral right to exercise the options. The contract was awarded on a cost-plus-fixed-fee
basis.
In 2008, after option 1 had been exercised, the parties entered into discussions
regarding the early exercise of a limited portion of the option 2 scope of work: the hot start-
up of the MFFF. NNSA designated the hot start-up scope of work as Early Option II or
âEO2.â In February 2008, the agency authorized MOX Services to begin incurring costs for
development of an EO2 proposal.
On May 20, 2008, NNSA and MOX Services bilaterally executed contract
modification A124 (mod A124), definitizing option 1. The modification includes, in clause
H.29, âAdvance Understandings,â the following language in paragraph (g):
DOE has determined an early exercise of the hot start-up portion of Option II
is in the best interest of the project to ensure that all aspects of the MFFF are
operational before acceptance of the MFFF. DOE commits to immediate
review [of] all of the issues associated with an early exercise of the hot start-up
and begin the process of placing hot start-up on contract. Part of these
activities will include the market research to determine whether or not the
Contractor is the only company that is capable of performing these activities.
If DOE determines that the Contractor is the only company capable of
performing the additional work scope, then both parties agree to enter into
good faith negotiations to add the additional work in accordance with H.6,
1
These four phases are described in a paragraph of DOEâs statement of
uncontested facts. MOX Services objects that â[t]o the extent [this paragraph] is a general
characterization of the options contained with the contract, the words and generalizations
used to describe the contract options are not, in and of themselves, relevant facts that may
be substituted for the text of the actual contract.â Nevertheless, MOX Services includes a
virtually identical description of the option phases in its own statement of uncontested facts.
Thus, the parties agree that the description is accurate.
CBCA 5395 3
Options To Extend Services. It is agreed that the following parameters shall
apply to the early exercise of hot start-up:
1) In recognition of the increased performance risk, an increased fee rate
of 1 percentage point shall be applied to the negotiated value of
Option 1, plus any fee bearing changes executed prior to definitization
of the Hot-start scope, thus increasing the total fee to 7%.
On November 25, 2008, a DOE contracting officer wrote to MOX Services, âAs
negotiated in Option 1, the Government has agreed to partially exercise Option 2, MFFF
Operations.