ASBCA 61408
Board: ASBCA
Agency: Defense Advanced Research Projects Agency
Appellant: Cellular Materials International, Inc.
Date: 2021-12-27
Outcome: denied
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Cellular Materials International, Inc. ) ASBCA No. 61408
)
Under Contract Nos. HR0011-10-C-0054 )
HR0011-10-C-0117 )
N00014-13-C-0201 )
W57HZV-10-C-0148 )
HR0011-14-C-0034 )
APPEARANCE FOR THE APPELLANT: Mr. Doug Long
CEO
APPEARANCES FOR THE GOVERNMENT: Arthur M. Taylor, Esq.
DCMA Chief Trial Attorney
Michael T. Patterson, Esq.
Trial Attorney
Defense Contract Management Agency
Chantilly, VA
OPINION BY ADMINISTRATIVE JUDGE OâCONNELL
ON CROSS-MOTIONS FOR SUMMARY JUDGMENT
This appeal involves a government claim arising from the difference between the
billing rates of appellant, Cellular Materials International, Inc. (CMI), and final rates
established by the contracting officer (CO). The parties have cross moved for summary
judgment. The Board grants the governmentâs motion and denies appellantâs motion.
STATEMENT OF FACTS FOR PURPOSES OF THE MOTION
The following facts are undisputed or uncontroverted.
This appeal arises from five contracts performed by CMI, including the above-
referenced representative contract awarded by the Defense Advanced Research Projects
Agency on April 28, 2010 (the Contract). The Contract provided for payment of cost
plus a fixed fee in the estimated total amount of $4,428,863 and included, among other
clauses, Federal Acquisition Regulation (FAR) FAR 52.216-7, ALLOWABLE COST
AND PAYMENT (DEC 2002). (R4, tab 1 at 2, 23) 1
1
When citing the Rule 4 file, we reference the .pdf page number for the digital version of
that document.
Pursuant to the requirements of this clause, CMI submitted final indirect cost
proposals for fiscal years 2010 â 2014 ((govât statement of undisputed material facts
(GSUMF) ¶¶ 6-9 (citing govât mot. at exs. G-2 to G-6)). Initially, the Defense Contract
Audit Agency (DCAA) informed CMI that its proposals were low risk and would not be
audited (GSUMF ¶ 16; R4, tab 9 at 6). But after receiving this notice, CMI revised its
2010-2014 proposals to add $425,000 ($85,000 per year) in general and administrative
(G&A) costs for a consultant, Mr. Haydn Wadley (id.; GSUMF ¶ 10). In addition to his
purported work as a consultant, Mr. Wadley was CMIâs largest shareholder, owning up to
about 39% of the shares during this period 2 (GSUMF ¶¶ 4, 10, 16; govât mot. at ex. G-1).
DCAA thereafter performed an audit and issued a report questioning all $425,000
in consultant costs. DCAA stated that the âcontractor was not able to provide invoices or
other support to include sufficient detail as to the time expended and nature of the actual
services provided by the consultant.â It also stated that Mr. Wadley had not been paid for
some of the services. (GSUMF ¶ 14 (citing R4, tab 8 at 6))
On August 22, 2017, the CO issued a final decision unilaterally establishing final
indirect cost rates and asserting a demand for payment of $511,119, which included the
$425,000 for Mr. Wadley (R4, tab 9). The CO concluded that âCMI has not provided
sufficient evidence of the nature and scope of the service furnished such that incurrence,
allowability, [and] allocability of these costs can be determined ...â (R4, tab 9 at 7).
After CMI filed a timely appeal, it produced to the government various
documents, including 31 canceled checks, that resulted in the government agreeing that
CMI had made $219,583.23 in payments to Mr. Wadley and that these payments were
allowable costs. The parties were also able to resolve the portion of the dispute that did
not relate to Mr. Wadley, which amounted to an additional $86,119. (GSUMF ¶¶ 16 n.5;
compl. ¶¶ 6-8)
The amount that remains in dispute is $205,416.57 (GSUMF ¶ 22; compl. ¶ 7). In
support of this amount, CMI has provided the government 27 promissory notes executed
each month from October 2012 to December 2014 in which CMI promised to pay
Mr. Wadley the amount of $7,083.33, for a total amount of $191,249.91. The notes do
not provide for interim payments or contain a date for repayment, other than to state that
they are payable five days after demand (R4, tab 6; GSUMF ¶¶ 21- 22). As an
explanation, Les Gonda, President and Chief Executive Officer of CMI, and Mr.